Factor e Farm Infrastructure Buildout 2011 Budget: Difference between revisions
Jump to navigation
Jump to search
(→Actual) |
No edit summary |
||
Line 33: | Line 33: | ||
*Oct. 6, 2011 - HabLab step edge excavation correction - $437.50 | *Oct. 6, 2011 - HabLab step edge excavation correction - $437.50 | ||
*Oct. 8, 2011 - 2 soil pulverizer Prototype 3s complete minus motors, bearings, and chain - $4006.18 | |||
*Oct. 10, 2011 - mowing (280), raking (140), baling (220), 20 acres, for insulation - $640.00 | |||
*Oct. 13, 2011 - 30" and 13"sawblades for Dimensional Sawmill prototype I, teeth, wrench - $1062.95 | |||
*Oct. 14, 2011 - additional gravel for HabLab, 17 tons, Apac - $254.79 | |||
*Oct. 14, 2011 - 9 + 6 cu yds concrete pour for HabLab walls, kitchen, bathroom, Payless Concrete - $1910.43 | |||
*Oct. 14, 2011 - lumber for HabLab roof and framing - $2742.03 | |||
*Oct. 14, 2011 - foundation form lumber, HabLab - $210.03 | |||
*Oct. 14, 2011 - roof tiedown threaded rod and nuts, MoKan Fastener - $67.22 | |||
*Oct. 14, 2011 - 5 hard hats - $52.18 | |||
*Oct. 14, 2011 - PowerCube muffler studs and nuts - $57.54 | |||
*Total Anonymous spending - ''$24,892.09'' |
Revision as of 18:31, 16 October 2011
Note that this budget includes equipment and materials mixed together
Phase 1: Shop Roofing and Preparation
- 4 Milwaukee cordless drills – $407
- Roof metal - 136 panels, 17' long (3' widths) - 108 for workshop, 22 for material shed, and 6 extra + flashing for clerestory + screws + flashing closure – $5871
- 2x6 lumber, 6.60 - total 396 pieces - $2802
- Glue, #25 star driver bits, 3" star bit screws, 2 glue guns, furring strips, 2 tie downs – $299
- Trailer rental for lumber – $47
- Gravel for OSE Shop 2011 - 5000 sq ft of 6" deep plus 4x4x3' pillar bases - $2703
- Dimensional sawmill prototype 1 - check mailed directly to Sweiger - $10,000
Phase 2: Foundations
- Sep. 29, 2011 -Excavation and bulldozing, Workshop and HabLab, Duffy Reynolds Construction - $4k
- Oct. 3, 2011 - Construction rebar, Sweiger - $3968.60
- Oct. 3, 2011 - LifeTrac bucket prototype 1, Sweiger - $828
- Oct. 3, 2011 - LifeTrac tracks chain for 3 tractors - $1046.97
- Oct. 3, 2011 - metal, hydraulic coolers, welding supplies, 2 generators - $2786.39
- Oct. 4, 2011 - foundation pads concrete, Payless Concrete - $821.28
- Oct. 6, 2011 - HabLab step edge excavation correction - $437.50
- Oct. 8, 2011 - 2 soil pulverizer Prototype 3s complete minus motors, bearings, and chain - $4006.18
- Oct. 10, 2011 - mowing (280), raking (140), baling (220), 20 acres, for insulation - $640.00
- Oct. 13, 2011 - 30" and 13"sawblades for Dimensional Sawmill prototype I, teeth, wrench - $1062.95
- Oct. 14, 2011 - additional gravel for HabLab, 17 tons, Apac - $254.79
- Oct. 14, 2011 - 9 + 6 cu yds concrete pour for HabLab walls, kitchen, bathroom, Payless Concrete - $1910.43
- Oct. 14, 2011 - lumber for HabLab roof and framing - $2742.03
- Oct. 14, 2011 - foundation form lumber, HabLab - $210.03
- Oct. 14, 2011 - roof tiedown threaded rod and nuts, MoKan Fastener - $67.22
- Oct. 14, 2011 - 5 hard hats - $52.18
- Oct. 14, 2011 - PowerCube muffler studs and nuts - $57.54
- Total Anonymous spending - $24,892.09