Matthew Schwabauer Proposal: Difference between revisions
(Created page with "==Matthew Schwabauer's Proposals== ===Factor e Farm Construction Director-First 3 Weeks=== I (Matthew Schwabauer) will work as Construction Director at Factor e Farm for an indef...") |
No edit summary |
||
Line 5: | Line 5: | ||
The Routine Breaks Down like this... | The Routine Breaks Down like this... | ||
'''Available Time''' | '''Available Time:'''Total Hours in Three Week Period | ||
3 wk * 7 da/wk * 24 hr/da = 504 hr | 3 wk * 7 da/wk * 24 hr/da = 504 hr | ||
'''Work Time''' | '''Life Time:'''Hours allocated to sleeping, eating, and general life maintenance | ||
3 wk * 7 da/wk * 11 hr/da = 231 hr | |||
'''Work Time:'''Hours allocated to Factor e Farm projects | |||
3 wk * 6 da/wk * 10 hr/da = 180 hr | 3 wk * 6 da/wk * 10 hr/da = 180 hr | ||
''' | '''Play Time:'''Hours allocated to personal development, interests, and relaxation | ||
3 wk * 6 da/wk * 3 hr/da + 3 wk * 1 da/wk * 13 hr/da = 93 hr | 3 wk * 6 da/wk * 3 hr/da + 3 wk * 1 da/wk * 13 hr/da = 93 hr | ||
'''Work Time''' can be further divided into | |||
'''Finishing the Factor e Motel:''' 90 hr | |||
'''Developing the Forestry and Sawmill Program:''' 30 hr | |||
'''Daily Documentation:''' 21 hr | |||
'''Planning the Microhouse:''' 20 hr | |||
'''Cross-Training and Farm Projects:''' 19 hr |
Revision as of 08:16, 23 June 2012
Matthew Schwabauer's Proposals
Factor e Farm Construction Director-First 3 Weeks
I (Matthew Schwabauer) will work as Construction Director at Factor e Farm for an indefinite period of time, starting July 1, 2012. I will move onto Factor e Farm on June 30, 2012. I will follow Matthew_Schwabauer_Schedule, contributing approximately 10 hours per day, 6 days per week, towards "Work." This Three Week period of work will concentrate on completing construction of the Five "Motel Rooms" on the East side of the Hablab. I will ensure that those 5 rooms are ready for move-in by July 21, 2012. I will thoroughly plan, execute, and document this process. I anticipate spending 90 hours of my time on this construction project. I anticipate needing 50 hours of assistance from other Open Source Ecologists, primarily as labor during the construction process. During my remaining 90 hours of work during this period I will provide a daily log of my activities (21 hours), initiate the Factor e Farm sawmill and forestry program (24 Hours), plan for the Microhouse (15 Hours), cross-train(10 Hours), provide cross-training(2 Hours), and contribute to farm projects(23 Hours).
The Routine Breaks Down like this...
Available Time:Total Hours in Three Week Period
3 wk * 7 da/wk * 24 hr/da = 504 hr
Life Time:Hours allocated to sleeping, eating, and general life maintenance
3 wk * 7 da/wk * 11 hr/da = 231 hr
Work Time:Hours allocated to Factor e Farm projects
3 wk * 6 da/wk * 10 hr/da = 180 hr
Play Time:Hours allocated to personal development, interests, and relaxation
3 wk * 6 da/wk * 3 hr/da + 3 wk * 1 da/wk * 13 hr/da = 93 hr
Work Time can be further divided into
Finishing the Factor e Motel: 90 hr
Developing the Forestry and Sawmill Program: 30 hr
Daily Documentation: 21 hr
Planning the Microhouse: 20 hr
Cross-Training and Farm Projects: 19 hr