(Created page with "==Matthew Schwabauer's Proposals== ===Factor e Farm Construction Director-First 3 Weeks=== I (Matthew Schwabauer) will work as Construction Director at Factor e Farm for an indef...")
 
No edit summary
Line 5: Line 5:
The Routine Breaks Down like this...
The Routine Breaks Down like this...


'''Available Time'''
'''Available Time:'''Total Hours in Three Week Period
 
3 wk * 7 da/wk * 24 hr/da = 504 hr
3 wk * 7 da/wk * 24 hr/da = 504 hr


'''Work Time'''
'''Life Time:'''Hours allocated to sleeping, eating, and general life maintenance
 
3 wk * 7 da/wk * 11 hr/da = 231 hr
 
'''Work Time:'''Hours allocated to Factor e Farm projects
 
3 wk * 6 da/wk * 10 hr/da = 180 hr
3 wk * 6 da/wk * 10 hr/da = 180 hr


'''Life Time'''
'''Play Time:'''Hours allocated to personal development, interests, and relaxation
3 wk * 7 da/wk * 11 hr/da = 231 hr


'''Play Time'''
3 wk * 6 da/wk * 3 hr/da + 3 wk * 1 da/wk * 13 hr/da = 93 hr
3 wk * 6 da/wk * 3 hr/da + 3 wk * 1 da/wk * 13 hr/da = 93 hr
'''Work Time''' can be further divided into
'''Finishing the Factor e Motel:''' 90 hr
'''Developing the Forestry and Sawmill Program:''' 30 hr
'''Daily Documentation:''' 21 hr
'''Planning the Microhouse:''' 20 hr
'''Cross-Training and Farm Projects:''' 19 hr

Revision as of 08:16, 23 June 2012

Matthew Schwabauer's Proposals

Factor e Farm Construction Director-First 3 Weeks

I (Matthew Schwabauer) will work as Construction Director at Factor e Farm for an indefinite period of time, starting July 1, 2012. I will move onto Factor e Farm on June 30, 2012. I will follow Matthew_Schwabauer_Schedule, contributing approximately 10 hours per day, 6 days per week, towards "Work." This Three Week period of work will concentrate on completing construction of the Five "Motel Rooms" on the East side of the Hablab. I will ensure that those 5 rooms are ready for move-in by July 21, 2012. I will thoroughly plan, execute, and document this process. I anticipate spending 90 hours of my time on this construction project. I anticipate needing 50 hours of assistance from other Open Source Ecologists, primarily as labor during the construction process. During my remaining 90 hours of work during this period I will provide a daily log of my activities (21 hours), initiate the Factor e Farm sawmill and forestry program (24 Hours), plan for the Microhouse (15 Hours), cross-train(10 Hours), provide cross-training(2 Hours), and contribute to farm projects(23 Hours).

The Routine Breaks Down like this...

Available Time:Total Hours in Three Week Period

3 wk * 7 da/wk * 24 hr/da = 504 hr

Life Time:Hours allocated to sleeping, eating, and general life maintenance

3 wk * 7 da/wk * 11 hr/da = 231 hr

Work Time:Hours allocated to Factor e Farm projects

3 wk * 6 da/wk * 10 hr/da = 180 hr

Play Time:Hours allocated to personal development, interests, and relaxation

3 wk * 6 da/wk * 3 hr/da + 3 wk * 1 da/wk * 13 hr/da = 93 hr


Work Time can be further divided into

Finishing the Factor e Motel: 90 hr

Developing the Forestry and Sawmill Program: 30 hr

Daily Documentation: 21 hr

Planning the Microhouse: 20 hr

Cross-Training and Farm Projects: 19 hr