=Introduction=
=Introduction=


This charts shows the per person time requirement for building out a complete infrasstructure, AND building the equipment base with 1 person
This charts shows the per person time requirement for building out a complete infrastructure, AND building the equipment base with 1 person. Note that the agriculture and construction is shared between 30 people, while fabricator training and eqiupment fabrication is done solo. This is because any community needs a minimum of only one master fabricator in terms of time requirements for maintaining lifetime design equipment. As a good community design, however, having as many fabricators as possible is a better design.


{|
{|

Revision as of 23:27, 22 March 2009

Introduction

This charts shows the per person time requirement for building out a complete infrastructure, AND building the equipment base with 1 person. Note that the agriculture and construction is shared between 30 people, while fabricator training and eqiupment fabrication is done solo. This is because any community needs a minimum of only one master fabricator in terms of time requirements for maintaining lifetime design equipment. As a good community design, however, having as many fabricators as possible is a better design.

ITEM DAYS REQUIRED per person
Nnuresery propagation 7
Animal setup 14
100 trees per day 7
4 raised beds per day 5
digging a well 1
swaling and ponds 15
1000 sq ft greenhouse 30
lumber milling 2
brick pressing 2
building 30
workshop training 60
equipment fabrication 180
TOTAL 353