Revision as of 13:48, 15 January 2026 by Marcin (talk | contribs) (Created page with "= May 1 Labor Target – Phase Breakdown (1,000 ft² Seed Eco-Home) = ''Assumptions:'' * Repeatable design, low roof complexity * Tight logistics (kitted, staged materials) * Minimal rework * Utilities not extreme * KPI = On-site person-hours (track prefab separately if applicable) == A) Site Prep & Foundation == * Scope: layout, excavation, foundation system, backfill/rough grade * Target: '''70–110 hours''' == B) Structural Shell == * Scope: floor (if any), walls,...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

May 1 Labor Target – Phase Breakdown (1,000 ft² Seed Eco-Home)

Assumptions:

  • Repeatable design, low roof complexity
  • Tight logistics (kitted, staged materials)
  • Minimal rework
  • Utilities not extreme
  • KPI = On-site person-hours (track prefab separately if applicable)

A) Site Prep & Foundation

  • Scope: layout, excavation, foundation system, backfill/rough grade
  • Target: 70–110 hours

B) Structural Shell

  • Scope: floor (if any), walls, roof, sheathing, WRB, dry-in
  • Target: 120–170 hours

C) Exterior Close

  • Scope: windows/doors, roofing, siding/cladding
  • Target: 60–90 hours

D) MEP (Mechanical, Electrical, Plumbing)

  • Scope: plumbing + electrical + HVAC rough/trim (simplified routing assumed)
  • Target: 100–150 hours

E) Insulation & Air Sealing

  • Scope: insulation install, air sealing details
  • Target: 20–35 hours

F) Interior Finishes

  • Scope: wall finish, paint, flooring, cabinets/trim, fixtures/appliances
  • Target: 110–170 hours

G) Commissioning, Punch, Cleanup

  • Scope: system checks, punch list, final clean
  • Target: 20–25 hours

Totals

  • Low-end total: 500 hours
  • High-end total: 750 hours

Measurement Protocol

  • Headline KPI: On-site person-hours (every human hour on site counts)
  • Include: supervisors, material handling, cleanup, rework, waiting
  • Exclude from headline (track separately): design/engineering, procurement/admin, marketing/sales
  • Optional secondary KPI: Total person-hours including off-site prefab

Build-Day Scorecard

Phase Actual Hours Target Variance
A) Site & Foundation 70–110
B) Structural Shell 120–170
C) Exterior Close 60–90
D) MEP 100–150
E) Insulation & Air Sealing 20–35
F) Interior Finishes 110–170
G) Commissioning 20–25
TOTAL 500–750