Pyrolysis Oil Project Status
Jump to navigation
Jump to search
Current Development Stage(s)
For the Deployment Stages see: Pyrolysis_Open_Source_Design_Rationale_(OSDR)#Deployment_Strategy
Model for Empirical Knowledge
- March 21st,2009 Purchased five feet of 3/4" copper pipe, five copper 3/4" 90 degree elbows, one 3/4" to 1/2" copper coupler, 10' feet of 1/2" nominal tubing, flux, silver solder, MAPP gas, torch head, pipe cutter, flux, silver solder, Dremel tool.
- March 21st,2009 Cut to length all five feet of copper pipe