Steps For Building a Solar Structure
Review of concept to date:
- CEB walls
- Straw bale infill between 2 wall cavities
- House-integrated CEB stove
- Thermaclear or Solexx glazing
- Structure similar to
but solar cover extends from green roof
- Greenspace
- Green roof
- Trellis for solar shade in summer
- Trellis is covered partly with roofing material with solar angle to allow for solar gain only in winter
- Rest of trellis will be growing grapes
- Composting toilet
- CEB floor
- Side space covered for rooftop rainwater catchment and CEB water cistern
- Planter in front and sides - zone 0 plantings in planter
- Keyhole garden
Steps
- Site prep - flatten site with front loader and blade
- Build blade
- Build LifeTrac II
- Build sawmill
- Building material prep
- Rollers
- Sawmilling in July
- Truss preparation
- Test stabilized bricks
- Test reject lime-cement bricks?#Initial experiments with
- Air-powered water pump
Summary: June-July will be shakedown of stabilized brick
Uniqueness summary: LifeTrac II, Sawmill, Air powered water pump, CEB stove, CEB floor, OS blade, PowerCube II, CEB-Straw Bale hybrid
Timeline
- April 15-30 - Dimensional Sawmill Prototype design
- Assuming 1 CEB presss production
- May 1-31 - Build LifeTrac II, PowerCube II, build Sawmill, build leveling blade, build LifeTrac wheel tracks if budget allows
- June - July - Cut lumber, test stabilized and lime bricks, do the well pump and prepare water lines, site preparation, build trusses, prepare brick rollers
- Test whether water-sraying between courses works (so called 'dry stacking'), or, prepare slurry mixing equipment (either 55 gal drum or 200 gal container)