Sara Kit Certification
Jump to navigation
Jump to search
Build Space
Make a copy of:
Main Checklist
Electronics Checklist
Build
Kit Build
Time Lapse
One can study the time lapse in detail to understand the build time. This time lapse should span about 7-8 hours. Rework time was about 1.2 hours.
Time Log
And comments. Time is in minutes. Negative sign - time to be subtracted and added to the Kit Prep phase, not Build Phase. Total time of build does not include negative times.
- 15:42 - Start. Unpack. Weld frame. Set up camera. Includes going from house to workshop. Time: Frame: 37-
- 16:19 - Axis assembly start. Y + Z rear. Missing tool: tape spacer. Time: 7
- 16:26 - Error warning: set screw allen wrench short side wore out mid way. Got another one. Time: -2
- 16:28-16:34 - Cleaning out idler pieces . Time: -7
- 16:35 - Tape on bearings. Not needed in practice. Time: -3
- 16:39 - Finished bearing insertion for all axes. Time: 2
- 16:56 - Y left finished - Time: 25 minutes
- 17:03 - Z back finished - Time - 7 minutes
- 17:15 - Y right, Z front done - Time - 12 minutes. Total for all axes outside of X - 44
- 17:23 - Y left and Z back axes mounted on frame. Time - 8
- 17:29 - Y right, Z front hung on frame - Time - 6
- 17:32 - Thermistor and PEI fix - Time - -3
- 17:35 - Glue PEI. Time - 13
- 17:48 - One heat bed nut was too small on the inside. Got another. -10
BREAK
- 18:53 - Nut catcher holes in idler pieces were droopy, reamed out to fit nuts. -2
- 18:55 - Z platform start.
- 18:58 - Z platform done (without bed attachment still) Time: 3
- 19:10 - X axis done. Time: 12 minutes.
- 19:15 - Y endstop glued on Y axis. Both endstops inserted into holders and one glued in. 5. Started power supply.
- 19:18 - 5 power supply screws came off. 1 was lost. Power supply power cord zip tie loose and below power supply. Power supply cord fixed to the top. Replaced screws. Time: -7
- 19:22 - Started control panel. MOSFET dangles forward.
- 19:37 - Control panel done. Time: 15
- 19:39 - Extruder sensor did not fit in extruder sensor holder. Reamed. Time: -1
- 20:10 - Extruder finished - Time: 32
- 20:21 - X axis mounted - Time: 11
Issues Log
- 2 top half circles of carriage pieces all had extra plastic on them. Needed cleaning.
- Thermistor head was on top face, not in hole:
Evaluation
Overall kit evaluation is this based on Kit Certification#Evaluation
Sara Comments and Improvements
Links
- Kit Certification
- Current Material inventory - [1]
- 3D Printer Logs - for parts production