Rough Plumbing Inspection Checklist
Jump to navigation
Jump to search
Detailed Checklist
Notes
- Each trap protected by vent
- See cleanout requirements.
- Ford Fitting for water supply line if supply line connection is inside the house.
- Water pressure test required
- Vacuum breakers on hose outlets
- Supply water line fill is inspected prior to covering
- Approved grounding system for water supply line?
- Tracer wire for water supply from meter to foundation
Sequencing
- Water Heater - Since it is a fixture [1] - a water heater is installed in the finish phase [2]
- Water heater is often installed at rough plumbing phase [3]
At Foundation Phase
- There may be an inspection during the foundatio phase.