Permitting and Inspection Log

From Open Source Ecology
Revision as of 21:12, 31 May 2022 by Marcin (talk | contribs) (→‎Tue May 31, 2022)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Tue May 31, 2022

Brian met David Marsh - JC KS #2021-8408, HAAG Certified Commercial & Residential Insp who had experience in the KCMO permit process who had some good insights on streamlining

  • 5 days is possible but after the foundation is in (because who knows what you find when you start digging and need to address)
  • if you get a master plan approved into the title block, you don't need designs approved again on future builds
  • you can hire an approved 3rd party inspector architecture/structural engineer to fast track the inspection process.