Drywall Finishing

From Open Source Ecology
Revision as of 05:21, 15 July 2024 by Marcin (talk | contribs) (→‎Time)
Jump to navigation Jump to search
  • How to hang drywall [1]
  • Tape and mud video [2]. Corner strip. 3 coats of mud over every edge or screw. Taping. Corners. Bulk sanding. Edge sanding. Ready to paint. Wow, lots of work.
  • How to mask - [3]. Use 3M fast masking - [4]
  • Power roller video - [5]

Time

  • One wall in a day -[6]. 5 hours for a wall with many penetrations.
  • 7 poeple, 4 days, 1000 sf - 224 hours [7]
  • 144 hrs 1000 sf [8]
  • Amateur takes 2400 hours for 3000 sf house [9]
  • 250-300 sheets with 2 man crew in 8-9 days [10], about half to hang and half to finish.
    • 16 sheets per person per day.