Truss Build Data Collection
Jump to navigation
Jump to search
Fri Jul 25, 2025
- Matthew Burnett - 22 of the 24' non-reinforced trusses - 12 hours excluding 30 min break. Already had 3 days of practice. Jig: 2x4 reinforcement cutout, end cutout for end piece nailsing. 25 1" 16 ga staples per side of bread on OSB scab, 2 scabs. 8 3" nails per side of break on 2' 2x4 scab, 16 3" nails per side of break on 4' 2x4 scab. OSB schedule - 6" with 2-3/8" nails. See the video tape for the first half. Included cutting more OSB scabs. OSB + 8' 2x4 was under tables. Finished product dragged on dolly assembly to outside. 2x4 16' long were outside south end of workshop. Jig was on north side of workshop.
Wed Jul 23, 2025
- Judy Scott - 4 of the 16' trusses in 6 hours, from beginning. All materials under table. 2x4x16 right outside shop. Pile outside shop. Thi s
Tue Jul 23, 2025
- MJ - 18 minute for non-reinforced 24' truss, 1/2"x16" OSB height like all rest. test of jig in north end of shop, without 2x4 scab cutouts. 2x4 scab cutouts implemented on Wednesday.