Max Log
Jump to navigation
Jump to search
Build Pictures
- Upload - [1]
Time Log
Write down morning work done, lunch time, and afternoon work done.
Tue Oct 28, 2025
Morning: 10:05am-12:45pm
- Installed 2nd sliding door handle/lock and adjusted roller (~5min total)
- Put up R38 fiberglass insulation into the ceiling, covered about 5 rows
Lunch: 12:45pm-1:45pm
Afternoon: 1:45pm-5:15pm
- Sealed cracks & gaps between wall modules & rafters/taper with spray foam
- Finished ceiling insulation in the first 2 house modules
- Started insulating wall modules in house module 1 with R19 fiberglass
- Started taking off some of the floor level OSB strips to fill in gaps behind them with spray foam (in house module 3)
Mon Oct 27, 2025
Morning: 10:05am-2:30pm
- Helped attach roof rafter braces
- Started attaching some PV panels
Lunch: 2:30pm-3:30pm
Afternoon: 3:30pm-6:20pm
- Measured out PV spacing on most runners
- Attached front PV mounts on most runners
- Finished installing first row of PV panels
Evening (non-work):
- Spent 2h after work learning/trying out FreeCAD 1.0