Write down morning work done, lunch time, and afternoon work done.

Fri Nov 7, 2025

Morning: -

Afternoon: 1:00pm-5:50pm

  • Installed back & front porch trim spacers
Front deck trim spacers
  • Started installing cedar shingles on front porch wall

Thu Nov 6, 2025

Morning: 10:20am-1:10pm

  • Installed 6x6 posts on front porch
Front deck posts

Afternoon: 2:30pm-5:50pm

  • Installed sheet metal roofing on front porch
Front deck roof metal

Wed Nov 5, 2025

Morning: 10:00am-12:45pm

  • Carried gravel bags onto roof
  • Shimmed & squared french door
French door shim

Lunch: 12:45pm-2:50pm

Afternoon: 2:50pm-5:50pm

  • Replaced front porch boards under french door
  • Lifted up all 3 front porch roof modules
  • Fixed rear of all 3 front porch roof modules to house wall
Front deck roof modules installed

Tue Nov 4, 2025

Morning: 10:30am-12:40pm

  • Added more screws to back porch sheet metal roof, was flapping in the wind
  • Started on french door installation
  • Installed tar flashing tape in french door frame
French door tar flashing tape

Lunch: 12:40pm-1:35pm

Afternoon: 1:35pm-5:05pm

  • Installed french door
French door installed
  • Leveled part of front porch a bit better to fit front porch wall
  • Installed second front porch wall
  • Carried all 3 front porch roof modules to front of building for installation

Mon Nov 3, 2025

Morning: 10:25am-2:40pm

  • Installed back porch walls
  • Built back porch 2nd roof module

Lunch: 2:40pm-3:55pm

Afternoon: 3:55pm-6:00pm

  • Installed back porch roof modules
  • Installed back porch 4x4 post
  • Installed back porch metal roofing
Rear deck

Sat Nov 1, 2025

Morning: 10:00am-12:00pm

  • Installed flashing tape on both sliding doors
Sliding door flashing tape
  • Built back veranda walls
Back veranda wall frames
Back veranda with wall siding installed

Lunch: -

Afternoon: 12:00pm-4:30pm

  • Leveled, positioned, and fixed front porch beneath sliding doors
Back veranda installed

Fri Oct 31, 2025

Morning: 10:25am-2pm

  • Finished 2nd window installation
Window sealed with tar tape


  • Build back veranda frame and installed planks
Back porch frame
Back veranda frame with planks installed

Lunch: 2pm-3:35pm

Afternoon: 3:35pm-7pm

  • Finished back veranda deck
  • Started back veranda wall frames
  • Screwed in 2nd rear veranda door frame

Thu Oct 30, 2025

Morning: 10:00am-12:00pm

  • Trimmed PV runners
PV runners flush with cap
  • Fixed up PV runner cap 2x4 on the 3rd module
  • Folded up roof membrane at the south side to fit with PV runner cap 2x4s
Wrapped & taped up end caps between modules
  • Installed some 1x6 roof trim
1x6 trim board on roof

Lunch: -

Afternoon: 12:00pm-6:45pm

  • Installed siding
Metal siding
  • Cut opening for east side windows
Cut window holes
  • Installed flashing tar tape on both window frames
Window flashing tape
  • Installed first window
Window installed.jpg
  • Started installation of second window

Wed Oct 29, 2025

Morning: 10:10am-12:15pm

  • Installed PV panels
Solar panels closeup
First row of solar panels installed

Lunch: 12:15pm-1:40pm

Afternoon: 1:40pm-7pm

  • Finished installing PV panels
Solar panel installation nearly complete
Solar panel installation complete
  • Trimmed roof membrane on east side of building to fit trim boards
  • Started installing trim boards on roof

Tue Oct 28, 2025

Morning: 10:05am-12:45pm

  • Installed 2nd sliding door handle/lock and adjusted roller (~5min total)
  • Put up R38 fiberglass insulation into the ceiling, covered about 5 rows

Lunch: 12:45pm-1:45pm

Afternoon: 1:45pm-5:15pm

  • Sealed cracks & gaps between wall modules & rafters/taper with spray foam
  • Finished ceiling insulation in the first 2 house modules
Ceiling insulation
  • Started insulating wall modules in house module 1 with R19 fiberglass
Wall insulation
  • Started taking off some of the floor level OSB strips to fill in gaps behind them with spray foam (in house module 3)

Mon Oct 27, 2025

Morning: 10:05am-2:30pm

  • Helped attach roof rafter braces
  • Started attaching some PV panels

Lunch: 2:30pm-3:30pm

Afternoon: 3:30pm-6:20pm

  • Measured out PV spacing on most runners
  • Attached front PV mounts on most runners
  • Finished installing first row of PV panels


Evening (non-work):

  • Spent 2h after work learning/trying out FreeCAD 1.0