Factor e Farm Infrastructure Buildout 2011
Jump to navigation
Jump to search
Introduction
2011 marks the buildout of Factor e Farm for the purpose of absorbing 12 people full time with comfortable accommodations and work space. The planned infrastructure buildout includes 6 superinsulated studios, 6 more 3-season studios, common kitchen, common shower/bathroom, electrical power infrastructure, and 3000 square foot workshop addition
Infrastructure Plan
We will allocate $60k to this project as follows:
- $1k - baler
- $4k - fully automatic CEB press (2 total)
- $3.5k -
- $2k - 20 kW-hr forklift battery bank
- $1k - 5 kW inverter, 24V
- $2k -