Seed Eco-Home Optimized Build Time
Jump to navigation
Jump to search
May 1 Labor Target – Phase Breakdown (1,000 ft² Seed Eco-Home)
Assumptions:
- Repeatable design, low roof complexity
- Tight logistics (kitted, staged materials)
- Minimal rework
- Utilities not extreme
- KPI = On-site person-hours (track prefab separately if applicable)
A) Site Prep & Foundation
- Scope: layout, excavation, foundation system, backfill/rough grade
- Target: 70–110 hours
B) Structural Shell
- Scope: floor (if any), walls, roof, sheathing, WRB, dry-in
- Target: 120–170 hours
C) Exterior Close
- Scope: windows/doors, roofing, siding/cladding
- Target: 60–90 hours
D) MEP (Mechanical, Electrical, Plumbing)
- Scope: plumbing + electrical + HVAC rough/trim (simplified routing assumed)
- Target: 100–150 hours
E) Insulation & Air Sealing
- Scope: insulation install, air sealing details
- Target: 20–35 hours
F) Interior Finishes
- Scope: wall finish, paint, flooring, cabinets/trim, fixtures/appliances
- Target: 110–170 hours
G) Commissioning, Punch, Cleanup
- Scope: system checks, punch list, final clean
- Target: 20–25 hours
Totals
- Low-end total: 500 hours
- High-end total: 750 hours
Measurement Protocol
- Headline KPI: On-site person-hours (every human hour on site counts)
- Include: supervisors, material handling, cleanup, rework, waiting
- Exclude from headline (track separately): design/engineering, procurement/admin, marketing/sales
- Optional secondary KPI: Total person-hours including off-site prefab
Build-Day Scorecard
| Phase | Actual Hours | Target | Variance |
|---|---|---|---|
| A) Site & Foundation | 70–110 | ||
| B) Structural Shell | 120–170 | ||
| C) Exterior Close | 60–90 | ||
| D) MEP | 100–150 | ||
| E) Insulation & Air Sealing | 20–35 | ||
| F) Interior Finishes | 110–170 | ||
| G) Commissioning | 20–25 | ||
| TOTAL | 500–750 |