OSE Roof Instructions
Jump to navigation
Jump to search
ASSEMBLY SHEET FOR WORKSHOP ROOF STRINGERS
- Cut one 16’ 2x6” beam to create one 10’8” piece and one 5’4” piece
- Cut one 16’ 2x6” beam to create one 10’ piece and one 6’ piece
- Cut two 16’ 2x6” beams to create two 11’ pieces and two 5’ pieces
- Cut one 16’ 2x6” beams to 14’ in length.
- Cut a diagonal piece off one 11’ piece and one full 16’ piece as shown.
- Lay out a 32’ assembly as shown in the diagram
- Spread glue on the 5-1/2” faces and screw together as shown in the detail at about 18” intervals.
- Lay out a 43” assembly as shown in the diagram.
- Spread glue on the 5-1/2” faces and screw together as shown in the detail at about 18” intervals.
Make 5 of each assembly
ASSEMBLY SHEET FOR SUPPLY SHED ROOF STRINGERS
- Cut four 16’ 2x6” beams to create four 10’8” pieces and four 5’4” pieces.
- Lay out a supply shed stringer assembly as shown in the diagram.
- Spread glue on the 5-1/2” faces and screw together as shown in the detail at about 18” intervals.