CEB Press/Manufacturing Instructions/Mount Solenoid Valve Set And Controller Box

From Open Source Ecology
Jump to navigation Jump to search

Video

Tools

  • Various Wrenches

Materials

  • 3/4" Quick Coupler Set (1)
  • SAE 12M to 3/4" Swivel (2)
  • SAE 6M to 1/2" Swivel (6)
  • Bolts and nuts for mounting on valve mount
  • 3/4"x1.5" Bolts (2)
  • 3/4" Nuts (2)
  • Prepared Controller Box
  • Prepared Controller Mount
  • Prepared Valve Mount

Fabrication

Install Controller

  • Bolt Controller Box to Controller Mount
  • Bolt controller mount to CEB.

Prepare Solenoid

  • Install the solenoid valves on the manifold in the order C-C-H, going from left to right, with the ports at the top.
  • Install the quick connect inlet and outlet in the side ports on the manifold. DON'T use thread tape for any connections to the manifold.
  • Onto the top of the manifold, install the 6 compression fittings into the A and B.

Install Solenoid on machine

Where to install the solenoid
Solenoidhoselocation.png
  • Bolt the solenoid to the valve mount.
  • Bolt the solenoid and valve mount to the primary arms on the assembled CEB.
  • Attach hoses from cylinders and shaker to manifold. See illustration for number locations.
    • 1=Main Cylinder Top
    • 2=Main Cylinder Bottom
    • 3=Secondary Cylinder Tee
    • 4=Secondary Cylinder Control Valve
    • 5=Shaker Non Return Line
    • 6=Shaker Return Line (Side with Needle Valve and Tee)