Month 1 Begins 6/18
Week 1 - workshop organizing
- Make magnets
 - Workshop cleanup and organizing
- Move tables
 - Draw up a technical workshop map
 - Moving and organizing on Friday
 
 - Keep learning Solidworks - whole month
 
Week 2 - Second Welding Table and Metal Rack
- Weld 2 more welding tables
- One needs to come from the old workshop
 - Assemble ironworker on new temporary welding table
 
 - Sketchup metal racks
 - Weld metal racks
- Stock metal
 - Sheet metal
 - Scrap
 
 - Keep Learning
 
Week 3 - Improving HabLab
- Transfer comforts/infrastructure responsibility of HabLab to Senior Schwabauer
- Shelving for Factor e Farm Library
 - Bedding
 - Sink retrofit
 - Bathroom retrofits
 - Power outlet finishing
 - Thermal and sound insulation
 - Winter stove
 
 - European Dish Drain
 
Week 4 - Plumbing and Tying Loose Ends
- Cars out and titles found -
 - Research and document ozonation
- Source ozonators for 1000 gallon and 5 gallon
 
 - Research bodet retrofit to toilets
 - Toilet-top sink