30 Person Village Startup with GVCS

From Open Source Ecology
Revision as of 23:24, 22 March 2009 by WikiSysop (talk | contribs) (Created page with '=Introduction= This charts shows the per person time requirement for building out a complete infrasstructure, AND building the equipment base with 1 person {| |ITEM | DAYS REQU...')
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Introduction

This charts shows the per person time requirement for building out a complete infrasstructure, AND building the equipment base with 1 person

ITEM DAYS REQUIRED per person
Nnuresery propagation 7
Animal setup 14
100 trees per day 7
4 raised beds per day 5
digging a well 1
swaling and ponds 15
1000 sq ft greenhouse 30
lumber milling 2
brick pressing 2
building 30
workshop training 60
equipment fabrication 180
TOTAL 353