July 11th, 2014

For next microhouse build should look to other microhouse construction workshops such as: PAD tiny houses workshops; a few things they do differently are early bird pricing, buddy discounts, more emphasis on classroom learning about logistics such as navigating codes, regulations, insurance, how to hook up house to water and power, etc

I think the networks that most need to be connected with (more so than natural builders or permaculturalists, etc) are: architects, urban designers, urban homesteaders


June 13th, 2014

Created a rough brochure for CEB press File:CEB press brouchure rough.pdf

June 12th, 2014

Continued gazebo work, measured out distances of supports, dug holes, stopped work due to structural problems in hexayurt roof (was a tension structure, so roof has no structural support) Helped with pool structure

June 11th, 2014

Began prep for building gazebo (weed whacked, drilled holes in 5 gallon bucked and installed rebar crosses and concrete for reinforcement, laid out stakes 85" and 60 degrees from each other)

June 10th, 2014

Finished installing exterior skin on laser cutter

Fri, June 6th, 2014

Drilled holes for exterior skin and plastic door panels using LasersaurSkinDrillHoles and Lasersaur's online manual

Thurs, June 5th, 2014

Lasersaur work: rerouted e-stop switch wiring to eliminate collision with exterior panels

Rerouted door switch wiring to eliminate collision with plastic door panel

Wed, June 4th 2014

Started drawer guide manual for CEB press File:Drawerguide.zip

Completed reassembly of CEB press

Tue, June 3rd 2014

Cleaned up workshop

Started brick press assembly

Mon, June 2nd 2014

Removed frame on power cube

Installed screen doors upside down on hablab

Flipped screen doors over