Build Phase Time Breakdown for SH6+

From Open Source Ecology
Jump to navigation Jump to search
May 1 Phase Targets (on-site person-hours) — ranges sum exactly to 500–750 hours
Phase Target Hours (Low–High) Notes / What’s inside
1) Site & Foundation 70–110 Layout, excavation, foundation system, backfill/rough grade
2) Structural Shell 120–170 Floor (if any), walls, roof, sheathing, WRB, dry-in
3) Exterior Close 60–90 Windows/doors, roofing, siding/cladding
4) MEP (All) 100–150 Plumbing + electrical + HVAC rough/trim (simplified routing assumed)
5) Insulation & Air Sealing 20–35 Insulation install + air sealing details
6) Interior Finishes 110–170 Wall finish, paint, flooring, cabinets/trim, fixtures/appliances
7) Commissioning, Punch, Cleanup 20–25 Test/commission, punch list, final clean
Total 500–750 Low-end sums to 500; high-end sums to 750