Foundation Plumbing Inspection
- There may be an inspection during the foundation phase.
Notes:
- 5 lb pressure on a gauge with 0.1 PSI increments per IRC P2503.9 [1]
- Final drainpipe - is covered to crown, and if step on it, it is not bouncing. But when is this done for a slab - we must have plumbing prior to pour?
- 3" pipe - 1/8" slope per foot.
- 2" pipe - must have 1/4" per foot slope on showers.
Sourcing
- See spreadsheet for SEH 2 [2]