May Production Run

From Open Source Ecology
Jump to navigation Jump to search

See blog post - http://blog.opensourceecology.org/2011/06/june-1-production-run-update/

Other documentation forthcoming.


Tasks Remaining

  • Outstanding Parts


Wheel Mounting

  • Drill 1-3/8" ends of shafts
  • Drill 3/4" hole for wheel mounting shafts
  • Cut wheel mounting gussets
  • CNC Torch Table Wheel Mounting plates (12)
  • CNC Torch Hydraulic motor interface plates (12)
  • CNC Torch Hydraulic motor plates (12)

Tractor Balance of Frame

  • Main lower hydraulic attachment plates (6 total)
  • Main upper hydraulic attachment plates (6 total)
  • Prepare valve mounting bar
  • Torch holes for Loader bars
  • Prepare loader bars
  • Loader cross support hole drilling

Holepuncher

  • Eyes for QA plates
  • Eyes for cylinder attachments
  • Main CEB frame holes
  • Arm holes for CEB
  • Hopper mount plate holes
  • Loader arm cross support plates

QA Plates

  • Specify QA mechanism
  • Do quick attach mechanisms (6 total, 2 per tractor)
  • Weld eyes to QA plates

CEB

  • Cut remaining frame pieces
  • Cut 3 more hopper sheets
  • Prepare hopper edge sealing strips