MicroHouse 4 Utilities
Test-Driven Requirements
- Water, septic tank, outdoor water hydrant, external 200A breaker and connection point for downstream 200A circuit, internet line
- Documentation of all line paths and burial depths
- Direct connection from street breaker panel to MicroHouse
- Electric power taken from panel on workshop via 0000 aluminum cable
- Attend to crossing points of internet, and attend to location of deeper water lines
- 1" poly pipe for water
- Power cable depth of 18"
- Water line depth of 36"
- Internet line depth of 18"
- Water teed into Hablab, and teed off for MicroHouse 3
- Underground water fittings are buried directly using corrosion-free fittings
- Leave provision for further extension of power grid from MicroHouse 3
2014 Utilities