To Tom G:
Thanks. See review:
http://opensourceecology.org/wiki/Power_Cube_VI_Review
So how would you feel about visiting us for 2 days to do a Collaborative Production Run of Prototype VII?
I propose we get full cad, fab drawings, fab diagram (see CEB blog post) - and full sourcing - and build in 2 days using a crew of 6 plus you as Guest Production Director? We've had 4-day results on the CEB press, not bad, but absolutely unprepared for and it should take 1 day next time with torch table. That's my plan.
Schedule
Collaborative Production run is slated for Nov 1-2 at present, Thu-Fri.