==Question 2== | ==Question 2== | ||
Is the mounting of rafters to the upper and lower mid truss strong enough? | Is the mounting of rafters to the upper and lower mid truss strong enough? Currently, there is a bird's mouth connection, but the upper end of the rafter is connected only at the bird's mouth. | ||
[[File:MidTruss1.jpg|500px]] | [[File:MidTruss1.jpg|500px]] |
Revision as of 17:07, 19 August 2014
MicroHouse Review Response Form
[ See Responses]
Review Request Document
Review Question Media
Question 1
Should the first floor bond beam go around the entire perimeter of the house? Note that the bond beam is split between 2 house levels. Should it go all around the house on top of level 1?
Error creating thumbnail: File missing
Question 2
Is the mounting of rafters to the upper and lower mid truss strong enough? Currently, there is a bird's mouth connection, but the upper end of the rafter is connected only at the bird's mouth.
Error creating thumbnail: File missing
Error creating thumbnail: File missing
Should cripple studs be added to connect the upper and lower 2x12’s and the rafters?
Error creating thumbnail: File missing
Question 3
In what order should the flashing, tar paper, and corrugated roofing be installed?
Error creating thumbnail: File missing