==Question 2==
==Question 2==
Is the mounting of rafters to the upper and lower mid truss strong enough?
Is the mounting of rafters to the upper and lower mid truss strong enough? Currently, there is a bird's mouth connection, but the upper end of the rafter is connected only at the bird's mouth.


[[File:MidTruss1.jpg|500px]]
[[File:MidTruss1.jpg|500px]]

Revision as of 17:07, 19 August 2014

MicroHouse Review Response Form


[ See Responses]

Review Request Document


edit this document

Review Question Media

Question 1

Should the first floor bond beam go around the entire perimeter of the house? Note that the bond beam is split between 2 house levels. Should it go all around the house on top of level 1?

Error creating thumbnail: File missing

Question 2

Is the mounting of rafters to the upper and lower mid truss strong enough? Currently, there is a bird's mouth connection, but the upper end of the rafter is connected only at the bird's mouth.

Error creating thumbnail: File missing
Error creating thumbnail: File missing

Should cripple studs be added to connect the upper and lower 2x12’s and the rafters?

Error creating thumbnail: File missing

Question 3

In what order should the flashing, tar paper, and corrugated roofing be installed?

Error creating thumbnail: File missing