Extreme Build Construction Agreement: Difference between revisions
Jump to navigation
Jump to search
(Created page with "=Scope= This is an agreement between OSE and a Extreme Build client. *The agreement is for a 1525 sf home, 1.5 story, as picturesd in Seed_Eco-Home. *This agreement is f...") |
|||
Line 11: | Line 11: | ||
=Responsibilities= | =Responsibilities= | ||
==OSE== | ==OSE== | ||
*Provides design, engineering | *Provides design, engineering calculations | ||
*Provide workshop leader and co-leader (currently Marcin + co-leader) | :*Provides stamped engineering drawings if needed | ||
*Provides a Workshop Manual documentation booklet for all participants | *Provide workshop leader and co-leader (currently Marcin + co-leader) on site for 1 full day before the event for prep, and during the 7 day event. | ||
*Posts event announcement and | *Provides a Workshop Manual documentation booklet for all participants | ||
*Posts event announcement and sign-up for participants | |||
*Secures food catering at a $15 per person per day budget | |||
*Orders all building materials for delivery at building site from standard sources | |||
*Secures all necessary small tools for the build - hammers, hard hats, drills, saws, | |||
*Visits site to inspect foundation and building materials, including pallets of bricks | |||
==Client== | ==Client== | ||
*Provides any requirements for OSE documentation (what documents are needed for approvals, permits) | *Provides any requirements for OSE documentation (what documents are needed for approvals, permits) | ||
*Provides lot description | *Provides lot description, picture | ||
*Takes OSE design and documentation and secures a building permit | *Takes OSE design and documentation and secures a building permit | ||
*Receives and inventories shipments of all materials and tools per checklist | |||
*Presses 7200 bricks, 4x6x12 inch | |||
*Stores bricks on 36-48 pallets, depending on | |||
*Submits 3 sample bricks to an independent testing lab for compressive strength | |||
*Stores all materials and protects them from rain until the build date. Stores CEBS under roof or cover. | |||
*Documents storage technique (sends picture of brick storage location) | |||
*Grades site, and prepares rubble trench foundation, sets forms, pours concrete, and makes plumbing/wiring allowances in foundation | |||
*Transports all brick pallets to building site to a carefully laid out location to streamline the build of walls (bricks as close to future walls as possible as here - [https://ksr-ugc.imgix.net/assets/012/925/942/89fdb157d8c7bdc327d19ec881f33f78_original.jpg?w=680&fit=max&v=1467388282&auto=format&q=92&s=345e41a30a67197359dcd791340e9671] | |||
*Provides covered workshop space of 1000 square foot minimum, with electricity for power tools, for construction of building modules during the workshop. | |||
*Provides air compressor for nail guns | |||
*Provides electricity or a generator for power at the building site. | |||
*Provides cement mixer for mixing clay slurry | |||
=Costs= | |||
*Client covers the cost of all materials ($30k) (detailed spreadheet) | |||
=Timeline= | |||
*Nov 16-22, 2018 - Build | |||
*Nov 14 by end of day - Arrival of OSE team | |||
*Oct 15, 2018 - 3rd party testing of sample bricks is performed | |||
*Oct 1, 2018 - Foundation is completed, 7200 bricks are pressed. | |||
*Aug 1, 2018 - Founndation is completed, Marcin arrives for foundation assessment, and trains brick press operator | |||
*Jul 1, 2018 - Permits are secured, and suitable soil is shipped to the building site ( | |||
=Contingencies= | |||
*If bricks are not pressed, the structure will be built with standard framed carpentry | |||
=Client Qeustionnaire= | |||
*What is the building address location |
Revision as of 02:52, 27 January 2018
Scope
This is an agreement between OSE and a Extreme Build client.
- The agreement is for a 1525 sf home, 1.5 story, as picturesd in Seed_Eco-Home.
- This agreement is for a house build only, not the Aquaponic Greenhouse, which is recommended as a future workshop.
- The entire build occurs during a 7 day period. Scope of build is:
- Structure
- Rooftop 3kW PV system with 12 motorcycle batteries,
- Rooftop water catchment system, 500 gallons
- on-demand hot-water fueled by propae off-the shelf space heating pellet stove, and
Responsibilities
OSE
- Provides design, engineering calculations
- Provides stamped engineering drawings if needed
- Provide workshop leader and co-leader (currently Marcin + co-leader) on site for 1 full day before the event for prep, and during the 7 day event.
- Provides a Workshop Manual documentation booklet for all participants
- Posts event announcement and sign-up for participants
- Secures food catering at a $15 per person per day budget
- Orders all building materials for delivery at building site from standard sources
- Secures all necessary small tools for the build - hammers, hard hats, drills, saws,
- Visits site to inspect foundation and building materials, including pallets of bricks
Client
- Provides any requirements for OSE documentation (what documents are needed for approvals, permits)
- Provides lot description, picture
- Takes OSE design and documentation and secures a building permit
- Receives and inventories shipments of all materials and tools per checklist
- Presses 7200 bricks, 4x6x12 inch
- Stores bricks on 36-48 pallets, depending on
- Submits 3 sample bricks to an independent testing lab for compressive strength
- Stores all materials and protects them from rain until the build date. Stores CEBS under roof or cover.
- Documents storage technique (sends picture of brick storage location)
- Grades site, and prepares rubble trench foundation, sets forms, pours concrete, and makes plumbing/wiring allowances in foundation
- Transports all brick pallets to building site to a carefully laid out location to streamline the build of walls (bricks as close to future walls as possible as here - [1]
- Provides covered workshop space of 1000 square foot minimum, with electricity for power tools, for construction of building modules during the workshop.
- Provides air compressor for nail guns
- Provides electricity or a generator for power at the building site.
- Provides cement mixer for mixing clay slurry
Costs
- Client covers the cost of all materials ($30k) (detailed spreadheet)
Timeline
- Nov 16-22, 2018 - Build
- Nov 14 by end of day - Arrival of OSE team
- Oct 15, 2018 - 3rd party testing of sample bricks is performed
- Oct 1, 2018 - Foundation is completed, 7200 bricks are pressed.
- Aug 1, 2018 - Founndation is completed, Marcin arrives for foundation assessment, and trains brick press operator
- Jul 1, 2018 - Permits are secured, and suitable soil is shipped to the building site (
Contingencies
- If bricks are not pressed, the structure will be built with standard framed carpentry
Client Qeustionnaire
- What is the building address location