=OSE Costs=
=OSE Costs=
*6 block per minute machine - 8 hour shift - 1 gallon per hour for CEB, 0.5 gallon per hour for tractor, one gallon per hour for soil mixer, local clay soil, 10% cement stabilized
*Total costs for 2880 block:
#2.5 gal* 8=20 gal fuel = $50 at current gas prices
#Cement - $10 per bag for 100 block - 29 bags of cement - $290
#Labor - $25/hr for tractor operator, $15/hr for stacking block on pallets x2 - $440/day
#Water - 20 ml/block = 58 liters = 15 gallons at 2 cents - 30 cents in water
Total costs -

Revision as of 00:35, 9 January 2020

Commercial

  • $1 for unstabilized, $1.20 for stabilized - [1]

OSE Costs

  • 6 block per minute machine - 8 hour shift - 1 gallon per hour for CEB, 0.5 gallon per hour for tractor, one gallon per hour for soil mixer, local clay soil, 10% cement stabilized
  • Total costs for 2880 block:
  1. 2.5 gal* 8=20 gal fuel = $50 at current gas prices
  2. Cement - $10 per bag for 100 block - 29 bags of cement - $290
  3. Labor - $25/hr for tractor operator, $15/hr for stacking block on pallets x2 - $440/day
  4. Water - 20 ml/block = 58 liters = 15 gallons at 2 cents - 30 cents in water

Total costs -