Line 9: | Line 9: | ||
*Full Product Releases: Tractor, Pulverizer, by May 21, 2011 , see [[Product Ecologies]] | *Full Product Releases: Tractor, Pulverizer, by May 21, 2011 , see [[Product Ecologies]] | ||
*See [[ | *See [[GVCS Tools Status]] | ||
[[Category:GVCS 50/2/2]] | [[Category:GVCS 50/2/2]] |
Revision as of 06:20, 29 March 2011
This is the log of an evolving strategic development plan for GVCS 50/2/2 - the goal of completing the GVCS in 2 years within a $2M budget.
Proposed Timeline
- Kickstarter campaign for the Open Source Microfactory- April 14
- Expected deliverables: $100k of funding for developing prototypes within 40 days of the date
- Full Product Releases: Tractor, Pulverizer, by May 21, 2011 , see Product Ecologies