Time to Build a House: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
(Added Another Category to The Page)
Line 11: Line 11:
*Framing - 225 hours per 1000 sf [https://www.quora.com/How-long-will-it-take-to-build-a-house?top_ans=82636192]
*Framing - 225 hours per 1000 sf [https://www.quora.com/How-long-will-it-take-to-build-a-house?top_ans=82636192]
*1100 sf mostly alone - 4 mos = 800 hours [https://www.quora.com/How-long-will-it-take-to-build-a-house?top_ans=82636192]
*1100 sf mostly alone - 4 mos = 800 hours [https://www.quora.com/How-long-will-it-take-to-build-a-house?top_ans=82636192]
*Summary - 2 man years per house - 6 men 4 mos. Size is assumed average of 2333 sf [https://www.google.com/search?q=average+size+of+new+hime&oq=average+size+of+new+hime&aqs=chrome..69i57.5934j0j4&client=ms-android-verizon&sourceid=chrome-mobile&ie=UTF-8]
*'''Summary''' - 2 man years per house - 6 men 4 mos. Size is assumed average of 2333 sf [https://www.google.com/search?q=average+size+of+new+hime&oq=average+size+of+new+hime&aqs=chrome..69i57.5934j0j4&client=ms-android-verizon&sourceid=chrome-mobile&ie=UTF-8]
*Or 2 man hours per sf average.
*Or 2 man hours per sf average.


[[Category: Housing and construction]] [[Category: Quick Reference]]
[[Category: Housing and construction]] [[Category: Quick Reference]]

Revision as of 14:26, 27 January 2022

  • 12 month owner builder, 8 month custom, 6 months spec [1]
  • 6 Month Spec - [2].
  • Habitat NOVA - 12-16 months during COVID (conference communications)

Hours

  • 1536 hours for a 600 sf house [3]. This would be 2600 hours for 1000 sf.
  • 1000 hours for 2000 sf - https://www.quora.com/How-many-man-days-does-it-take-to-build-a-typical-residential-house] assuming 6 day weeks of 8 hrs and one month of time with 5 person crew. Really?
  • 2 people 3 months 1500 sf [4] = 1200 hours
  • 3 guys 1 week 1200 sf [5]
  • 4 months 6 men efficient build, 3br. Say it's 2000 sf - 4 mos * 960 (40*6 men *4 weeks) = 4000 hours. 2 man years per house. [6]
  • Framing - 225 hours per 1000 sf [7]
  • 1100 sf mostly alone - 4 mos = 800 hours [8]
  • Summary - 2 man years per house - 6 men 4 mos. Size is assumed average of 2333 sf [9]
  • Or 2 man hours per sf average.