Rough Plumbing Inspection Checklist: Difference between revisions
Jump to navigation
Jump to search
(→Notes) |
|||
Line 3: | Line 3: | ||
=Notes= | =Notes= | ||
*DWV - 5 psi air or water. See that valve holds. 0.1 psi graded valve. | |||
*Each trap protected by vent | *Each trap protected by vent | ||
*See cleanout requirements. | *See cleanout requirements. |
Revision as of 07:41, 2 April 2022
Detailed Checklist
Notes
- DWV - 5 psi air or water. See that valve holds. 0.1 psi graded valve.
- Each trap protected by vent
- See cleanout requirements.
- Ford Fitting for water supply line if supply line connection is inside the house.
- Water pressure test required
- Vacuum breakers on hose outlets
- Supply water line fill is inspected prior to covering
- Approved grounding system for water supply line?
- Tracer wire for water supply from meter to foundation
Sequencing
- Water Heater - Since it is a fixture [1] - a water heater is installed in the finish phase [2]
- Water heater is often installed at rough plumbing phase [3]