Rough Plumbing Inspection Checklist: Difference between revisions
Jump to navigation
Jump to search
(→Notes) |
(→Notes) |
||
Line 12: | Line 12: | ||
*Approved grounding system for water supply line? | *Approved grounding system for water supply line? | ||
*Tracer wire for water supply from meter to foundation | *Tracer wire for water supply from meter to foundation | ||
*Toilet clearance 15" from sides and 12" from back | |||
=Sequencing= | =Sequencing= |
Revision as of 07:44, 2 April 2022
Detailed Checklist
Notes
- DWV - 5 psi air or water. See that valve holds. 0.1 psi graded valve.
- Each trap protected by vent
- See cleanout requirements.
- Ford Fitting for water supply line if supply line connection is inside the house.
- 125 Water pressure test required
- Vacuum breakers on hose outlets
- Supply water line fill is inspected prior to covering
- Approved grounding system for water supply line?
- Tracer wire for water supply from meter to foundation
- Toilet clearance 15" from sides and 12" from back
Sequencing
- Water Heater - Since it is a fixture [1] - a water heater is installed in the finish phase [2]
- Water heater is often installed at rough plumbing phase [3]