- The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [1]
- Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [2]
OSE Case
- No insulation covers any wiring or plumbing work.
- Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing.
- Smoke detectors are required on the electrical side - [3]
Links
- Plumbing Inspection - foundation, rough-in, final
- KC Inspections