<html> | <html> <iframe src="https://docs.google.com/presentation/d/e/2PACX-1vRroELe_ro8f1i8X-Ve6mby0VtpZCdfZyCuGtt1XJhqTq8l_DgBn5Lf1TaDw8dkTcTQmNVmun01GZNN/embed?start=false&loop=false&delayms=3000" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe> </html> | ||
[https://docs.google.com/presentation/d/12n4SwRb0DqMErBPWwkBZuGAK5b7XWYo56pK3GgHIjYo/edit#slide=id.g159201eb9bd_1_26 edit] | [https://docs.google.com/presentation/d/12n4SwRb0DqMErBPWwkBZuGAK5b7XWYo56pK3GgHIjYo/edit#slide=id.g159201eb9bd_1_26 edit] |
Latest revision as of 19:31, 5 October 2022
- Can CSED main cable clamp be directed inwards so screws are accessible for tightening? Otherwise need to ream out the inside.
- For flange-mount electrical boxes - when the box is fixed to the wall - must all the screws be already used on the flange, or can a temporary attachment be made?
- If not, is there any other allowable means of temporary attachment that others use or may be used? (fishing for efficiency detail)
- For the heat pump disconnect, is a nonmetallic push-in connector acceptable as a a clamping means for 10/2 cable for the incoming line, or do I need to use a NM cable clamp connector? 1/2" knockouts which are listed for 14-2 through 10-3 - does this apply to the push-in connectors as well?
- Will old work box be allowed on ceiling of 2nd floor bathroom if we put in ceiling first and light later - or must we cut a light hole out in panels first and then mount panel over light box?
- Is burying the ground rods required by code?
- Is it ok to wire neutral connection at a receptacle or do I need a pigtail?