The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [https://www.bartowcountyga.gov/Typical%20Order%20of%20Inspections_06-17-16.pdf]
=Sequence=
*The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [https://www.bartowcountyga.gov/Typical%20Order%20of%20Inspections_06-17-16.pdf]
*Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [https://inspectusa.com/blog/pre-drywall-inspection-and-scheduling-inspection/#:~:text=A%20Pre%2Ddrywall%20inspection%20should,IN%E2%80%9D%20portion%20of%20the%20project.&text=When%20everything%20is%20100%25%20completed,signed%20off%2C%20ready%20for%20insulation.]
*Thus - is there a separate inspection for insulation prior to all sheathing?
=OSE Case=
*No insulation covers any wiring or plumbing work.
*Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing.
*Smoke detectors are required on the electrical side - [https://www.cityofeasley.com/Rough-In%20Inspection%20Checklist.pdf]
 
=Extreme Inspection Schedules=
Some locations may have a large number of inspections, ideally these can occur on the same day if there are multiple similar ones. See [https://www2.minneapolismn.gov/media/content-assets/www2-documents/business/wcmsp-204538.pdf]. This calls for:
#Excavation
#Foundation
#Underground plumbing
#Rough plumbing/electrical
#Framing
#Insulation/vapor barrier - 2 inspections if foundation has exterior insulation
#Final plumbing/mechanical
#Final inspection. All done, street number and landscaping done.
 
=Links=
*[[Foundation Inspection]]
*[[Plumbing Inspection]] - foundation, rough-in, final
**[[Foundation Plumbing Inspection]]
**[[Rough-In Plumbing Inspection]]
**[[Final Plumbing Inspection]]
*[[Electrical Inspection]]
*[[KC Inspections]]
*[[Feedback_on_Inspection_Schedule]]
*[[Rough-In Electrical Inspection]]
*{{check}}'''[[Under Construction Phase Inspections]]'''
*{{check}}'''[[Seed Eco-Home Inspection Planning]]'''

Latest revision as of 00:13, 16 October 2022

Sequence

  • The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [1]
  • Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [2]
  • Thus - is there a separate inspection for insulation prior to all sheathing?

OSE Case

  • No insulation covers any wiring or plumbing work.
  • Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing.
  • Smoke detectors are required on the electrical side - [3]

Extreme Inspection Schedules

Some locations may have a large number of inspections, ideally these can occur on the same day if there are multiple similar ones. See [4]. This calls for:

  1. Excavation
  2. Foundation
  3. Underground plumbing
  4. Rough plumbing/electrical
  5. Framing
  6. Insulation/vapor barrier - 2 inspections if foundation has exterior insulation
  7. Final plumbing/mechanical
  8. Final inspection. All done, street number and landscaping done.