=Sequence= | |||
*The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [https://www.bartowcountyga.gov/Typical%20Order%20of%20Inspections_06-17-16.pdf] | *The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [https://www.bartowcountyga.gov/Typical%20Order%20of%20Inspections_06-17-16.pdf] | ||
*Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [https://inspectusa.com/blog/pre-drywall-inspection-and-scheduling-inspection/#:~:text=A%20Pre%2Ddrywall%20inspection%20should,IN%E2%80%9D%20portion%20of%20the%20project.&text=When%20everything%20is%20100%25%20completed,signed%20off%2C%20ready%20for%20insulation.] | *Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [https://inspectusa.com/blog/pre-drywall-inspection-and-scheduling-inspection/#:~:text=A%20Pre%2Ddrywall%20inspection%20should,IN%E2%80%9D%20portion%20of%20the%20project.&text=When%20everything%20is%20100%25%20completed,signed%20off%2C%20ready%20for%20insulation.] | ||
*Thus - is there a separate inspection for insulation prior to all sheathing? | |||
=OSE Case= | =OSE Case= | ||
*No insulation covers any wiring or plumbing work. | *No insulation covers any wiring or plumbing work. | ||
*Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing. | *Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing. | ||
*Smoke detectors are required on the electrical side - [https://www.cityofeasley.com/Rough-In%20Inspection%20Checklist.pdf] | *Smoke detectors are required on the electrical side - [https://www.cityofeasley.com/Rough-In%20Inspection%20Checklist.pdf] | ||
=Extreme Inspection Schedules= | |||
Some locations may have a large number of inspections, ideally these can occur on the same day if there are multiple similar ones. See [https://www2.minneapolismn.gov/media/content-assets/www2-documents/business/wcmsp-204538.pdf]. This calls for: | |||
#Excavation | |||
#Foundation | |||
#Underground plumbing | |||
#Rough plumbing/electrical | |||
#Framing | |||
#Insulation/vapor barrier - 2 inspections if foundation has exterior insulation | |||
#Final plumbing/mechanical | |||
#Final inspection. All done, street number and landscaping done. | |||
=Links= | =Links= | ||
*[[Foundation Inspection]] | |||
*[[Plumbing Inspection]] - foundation, rough-in, final | |||
**[[Foundation Plumbing Inspection]] | |||
**[[Rough-In Plumbing Inspection]] | |||
**[[Final Plumbing Inspection]] | |||
*[[Electrical Inspection]] | |||
*[[KC Inspections]] | *[[KC Inspections]] | ||
*[[Rough-In | *[[Feedback_on_Inspection_Schedule]] | ||
*[[Rough-In Electrical Inspection]] | |||
*{{check}}'''[[Under Construction Phase Inspections]]''' | |||
*{{check}}'''[[Seed Eco-Home Inspection Planning]]''' |
Latest revision as of 00:13, 16 October 2022
Sequence
- The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [1]
- Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [2]
- Thus - is there a separate inspection for insulation prior to all sheathing?
OSE Case
- No insulation covers any wiring or plumbing work.
- Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing.
- Smoke detectors are required on the electrical side - [3]
Extreme Inspection Schedules
Some locations may have a large number of inspections, ideally these can occur on the same day if there are multiple similar ones. See [4]. This calls for:
- Excavation
- Foundation
- Underground plumbing
- Rough plumbing/electrical
- Framing
- Insulation/vapor barrier - 2 inspections if foundation has exterior insulation
- Final plumbing/mechanical
- Final inspection. All done, street number and landscaping done.