Inspection Schedule: Difference between revisions
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
	
| No edit summary |  (→Links) | ||
| (2 intermediate revisions by the same user not shown) | |||
| Line 7: | Line 7: | ||
| *Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing. | *Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing. | ||
| *Smoke detectors are required on the electrical side - [https://www.cityofeasley.com/Rough-In%20Inspection%20Checklist.pdf] | *Smoke detectors are required on the electrical side - [https://www.cityofeasley.com/Rough-In%20Inspection%20Checklist.pdf] | ||
| =Extreme Inspection Schedules= | |||
| Some locations may have a large number of inspections, ideally these can occur on the same day if there are multiple similar ones. See [https://www2.minneapolismn.gov/media/content-assets/www2-documents/business/wcmsp-204538.pdf]. This calls for: | |||
| #Excavation | |||
| #Foundation | |||
| #Underground plumbing | |||
| #Rough plumbing/electrical | |||
| #Framing | |||
| #Insulation/vapor barrier - 2 inspections if foundation has exterior insulation | |||
| #Final plumbing/mechanical | |||
| #Final inspection. All done, street number and landscaping done. | |||
| =Links= | =Links= | ||
| *[[Foundation Inspection]] | |||
| *[[Plumbing Inspection]] - foundation, rough-in, final | *[[Plumbing Inspection]] - foundation, rough-in, final | ||
| **[[Foundation Plumbing Inspection]] | **[[Foundation Plumbing Inspection]] | ||
Latest revision as of 00:13, 16 October 2022
Sequence
- The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [1]
- Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [2]
- Thus - is there a separate inspection for insulation prior to all sheathing?
OSE Case
- No insulation covers any wiring or plumbing work.
- Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing.
- Smoke detectors are required on the electrical side - [3]
Extreme Inspection Schedules
Some locations may have a large number of inspections, ideally these can occur on the same day if there are multiple similar ones. See [4]. This calls for:
- Excavation
- Foundation
- Underground plumbing
- Rough plumbing/electrical
- Framing
- Insulation/vapor barrier - 2 inspections if foundation has exterior insulation
- Final plumbing/mechanical
- Final inspection. All done, street number and landscaping done.