Rough Plumbing Inspection Checklist: Difference between revisions
Jump to navigation
Jump to search
(→Videos) |
|||
(39 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
=Status of Completion= | |||
*Connection to water and sewer is made for the rough-in plumbing phase. [https://www.kulksplumbing.com/rough-in-plumbing-vs-finish-plumbing/#:~:text=During%20The%20Rough%20In%20Plumbing%20Phase%3A&text=Drain%20lines%20and%20water%20supply,a%20primary%20structure%20is%20completed.] | |||
=Detailed Checklist= | =Detailed Checklist= | ||
https://mybuildingpermit.com/sites/default/files/inline-files/IC_Residential_Plumbing-Rough-In_Final.pdf | https://mybuildingpermit.com/sites/default/files/inline-files/IC_Residential_Plumbing-Rough-In_Final.pdf | ||
=Videos= | |||
*To test water lines - pressurize through the washer box - [https://www.youtube.com/watch?v=z7NKLRiD8hM] - gauge on one line, air pressure on other. | |||
*Short overview, doesn't say much but gets you into the inspector mood - [https://www.youtube.com/watch?v=JKzca-Hqurw] | |||
*Relatively comprehensive video, with tub-shower pre-plumbed so none of its drain detail is shown: | |||
<html><iframe width="560" height="315" src="https://www.youtube.com/embed/oP17jzfq_HE" title="YouTube video player" frameborder="0" allow="accelerometer; autoplay; clipboard-write; encrypted-media; gyroscope; picture-in-picture" allowfullscreen></iframe></html> | |||
*Or, see how inefficient it gets for a larger house - 6000 sf of concrete after rough plumbing - 150 yards - like 18 trucks/ Shows stressing of foundation cables [https://youtu.be/eOlGmovAQg0?t=561]. Including copper pipe water service. | |||
*Waste and water pressure testing - plugging all holes - showing different plugs , [https://www.youtube.com/watch?v=p3LUGlH10ek]. | |||
*The washing machine box - trim cover at end is adjusted to thickness of sheathing [https://youtu.be/EzMURfc3Fgo?t=641] | |||
*Good one which shows what the inspector actually does - but this is not rough plumbing - just house plumbing inspection for home valuation purposes - [https://www.youtube.com/watch?v=pPp03QztEXo] | |||
<html><iframe width="560" height="315" src="https://www.youtube.com/embed/pPp03QztEXo" title="YouTube video player" frameborder="0" allow="accelerometer; autoplay; clipboard-write; encrypted-media; gyroscope; picture-in-picture" allowfullscreen></iframe></html> | |||
=Notes= | =Notes= | ||
*Each trap protected by vent | *DWV - 5 psi air or water. See that valve holds. 0.1 psi graded valve. | ||
**How do you stop the bath tub overflow? Drain should close, but overflow | |||
*Each trap protected by vent within allowed distance | |||
*See cleanout requirements. | *See cleanout requirements. | ||
*[[Ford Fitting]] for water supply line if supply line connection is inside the house. | *[[Ford Fitting]] for water supply line if supply line connection is inside the house. | ||
*Water pressure test required | *125 Water pressure test required | ||
*Vacuum breakers on hose outlets | *Vacuum breakers on hose outlets | ||
*Supply water line fill is inspected prior to covering | *Supply water line fill is inspected prior to covering | ||
*Approved grounding system for water supply line? | *Approved grounding system for water supply line? | ||
*Tracer wire for water supply from meter to foundation | *Tracer wire for water supply from meter to foundation | ||
*Toilet clearance 15" from sides and 12" from back | |||
*Nail plates for vent pipe - if you have sheathing above vents. | |||
*Tape for joints in vents must be '''UL 181''' listed. [https://youtu.be/o2SZUln1zH4?t=533] | |||
*Exterior wall water lines must be freeze protected. [https://youtu.be/o2SZUln1zH4?t=574] | |||
*Max 32" between PEX line supports. [https://youtu.be/o2SZUln1zH4?t=584]. Attach so that water hammer does not end up making noise. | |||
*Backflow preventer from street sewer. | |||
*Tubs are level - so you simplify the trim work necessary around it [https://youtu.be/ix6LPftLHP4?t=999] | |||
*Toilet 12.5" from framing, or 12 from wall. [https://youtu.be/ix6LPftLHP4?t=1244] | |||
*Caulk around toilet and bath? | |||
*Functional water flow test - [https://youtu.be/pPp03QztEXo?t=674] | |||
*2 parts vinegar + 1 part baking soda as alt to Drano [https://youtu.be/zzGWwsEmL7U?t=119] | |||
==Tub== | |||
*If tub is preinstalled, how to close overflow? ''The over flow I capped off by making a plate to screw on and used a piece of mouse pad as a gasket.'' [https://terrylove.com/forums/index.php?threads/proper-way-to-test-rough-in-with-tubs.16799/] | |||
**If tub is on second floor, its overflow can be the high water mark, so there is no need to close it. This would not apply if testing with air. | |||
*For rough-in, the easiest approach to tub in our case (it doesn't fit through doors, so must be pre-located. Pre-located does not mean it has to be pre-plumbed. So leave the drain kit off - just make sure it is possible to install it _after_ the trap is installed. | |||
*Assumes that trap doesn't have to be in for rough plumbing - just rough drain for tub. [https://www.finehomebuilding.com/forum/testing-plumbing-drain-systems-for-inspection] | |||
=Sequencing= | =Sequencing= | ||
*'''Water Heater''' - Since it is a fixture [https://www.google.com/search?sxsrf=ALeKk026QG9BbsZl0rNsBS9KmerMgczY_w%3A1602863734253&source=hp&ei=dsKJX6q8DJDYsAXHkpG4Cw&q=is+a+water+heater+a+fixture&btnK=Google+Search&oq=how+to+configure+nvidia+geforce+gtx+1650+super+on+linux+mint&gs_lcp=CgZwc3ktYWIQAzIFCCEQoAEyBQghEKsCMgUIIRCrAjoOCAAQ6gIQtAIQmgEQ5QI6DgguELEDEMcBEKMCEJMCOggILhDHARCvAToLCC4QsQMQxwEQowI6CAgAELEDEIMBOggILhCxAxCDAToFCAAQsQM6AggAOgQIABAKOgYIABAWEB46CAghEBYQHRAeOgcIIRAKEKABUMsQWOmzAWD8tAFoBnAAeACAAeQGiAGhS5IBDTExLjQ3LjMuMi42LTGYAQCgAQGqAQdnd3Mtd2l6sAEG&sclient=psy-ab&ved=0ahUKEwiqz4DcvLnsAhUQLKwKHUdJBLcQ4dUDCAk&uact=5] - a water heater is installed in the finish phase [https://kramerplumbingandradiantheat.com/stages-of-plumbing/] | *'''Water Heater''' - Since it is a fixture [https://www.google.com/search?sxsrf=ALeKk026QG9BbsZl0rNsBS9KmerMgczY_w%3A1602863734253&source=hp&ei=dsKJX6q8DJDYsAXHkpG4Cw&q=is+a+water+heater+a+fixture&btnK=Google+Search&oq=how+to+configure+nvidia+geforce+gtx+1650+super+on+linux+mint&gs_lcp=CgZwc3ktYWIQAzIFCCEQoAEyBQghEKsCMgUIIRCrAjoOCAAQ6gIQtAIQmgEQ5QI6DgguELEDEMcBEKMCEJMCOggILhDHARCvAToLCC4QsQMQxwEQowI6CAgAELEDEIMBOggILhCxAxCDAToFCAAQsQM6AggAOgQIABAKOgYIABAWEB46CAghEBYQHRAeOgcIIRAKEKABUMsQWOmzAWD8tAFoBnAAeACAAeQGiAGhS5IBDTExLjQ3LjMuMi42LTGYAQCgAQGqAQdnd3Mtd2l6sAEG&sclient=psy-ab&ved=0ahUKEwiqz4DcvLnsAhUQLKwKHUdJBLcQ4dUDCAk&uact=5] - a water heater is installed in the finish phase [https://kramerplumbingandradiantheat.com/stages-of-plumbing/] | ||
*Water heater is often installed at rough plumbing phase [https:// | *Water heater is often installed at rough plumbing phase [https://kramerplumbingandradiantheat.com/stages-of-plumbing/] | ||
=At Foundation Phase= | |||
*See [[Foundation Plumbing Inspection]] | |||
=Links= | =Links= | ||
*[[Plumbing Inspection]] | *[[Plumbing Inspection]] |
Latest revision as of 00:22, 16 October 2022
Status of Completion
- Connection to water and sewer is made for the rough-in plumbing phase. [1]
Detailed Checklist
Videos
- To test water lines - pressurize through the washer box - [2] - gauge on one line, air pressure on other.
- Short overview, doesn't say much but gets you into the inspector mood - [3]
- Relatively comprehensive video, with tub-shower pre-plumbed so none of its drain detail is shown:
- Or, see how inefficient it gets for a larger house - 6000 sf of concrete after rough plumbing - 150 yards - like 18 trucks/ Shows stressing of foundation cables [4]. Including copper pipe water service.
- Waste and water pressure testing - plugging all holes - showing different plugs , [5].
- The washing machine box - trim cover at end is adjusted to thickness of sheathing [6]
- Good one which shows what the inspector actually does - but this is not rough plumbing - just house plumbing inspection for home valuation purposes - [7]
Notes
- DWV - 5 psi air or water. See that valve holds. 0.1 psi graded valve.
- How do you stop the bath tub overflow? Drain should close, but overflow
- Each trap protected by vent within allowed distance
- See cleanout requirements.
- Ford Fitting for water supply line if supply line connection is inside the house.
- 125 Water pressure test required
- Vacuum breakers on hose outlets
- Supply water line fill is inspected prior to covering
- Approved grounding system for water supply line?
- Tracer wire for water supply from meter to foundation
- Toilet clearance 15" from sides and 12" from back
- Nail plates for vent pipe - if you have sheathing above vents.
- Tape for joints in vents must be UL 181 listed. [8]
- Exterior wall water lines must be freeze protected. [9]
- Max 32" between PEX line supports. [10]. Attach so that water hammer does not end up making noise.
- Backflow preventer from street sewer.
- Tubs are level - so you simplify the trim work necessary around it [11]
- Toilet 12.5" from framing, or 12 from wall. [12]
- Caulk around toilet and bath?
- Functional water flow test - [13]
- 2 parts vinegar + 1 part baking soda as alt to Drano [14]
Tub
- If tub is preinstalled, how to close overflow? The over flow I capped off by making a plate to screw on and used a piece of mouse pad as a gasket. [15]
- If tub is on second floor, its overflow can be the high water mark, so there is no need to close it. This would not apply if testing with air.
- For rough-in, the easiest approach to tub in our case (it doesn't fit through doors, so must be pre-located. Pre-located does not mean it has to be pre-plumbed. So leave the drain kit off - just make sure it is possible to install it _after_ the trap is installed.
- Assumes that trap doesn't have to be in for rough plumbing - just rough drain for tub. [16]
Sequencing
- Water Heater - Since it is a fixture [17] - a water heater is installed in the finish phase [18]
- Water heater is often installed at rough plumbing phase [19]