Seed Eco-Home 5 Data Collection: Difference between revisions
Jump to navigation
Jump to search
(→Totals) |
No edit summary |
||
Line 1: | Line 1: | ||
*Staking of forms - 1 hr for | *Staking of forms - 1 hr for 'supercorners', 2 hours for all rest including string. Superstructure concept works. | ||
*2 days of forms = 1 day 6 hours 6 people, day 2 from 8 to 1 PM = 66 hours + staking + grading | *2 days of forms = 1 day 6 hours 6 people, day 2 from 8 to 1 PM = 66 hours + staking + grading | ||
*Grading - 2 people 6+8 hours = 14 hrs pre-grade | *Grading - 2 people 6+8 hours = 14 hrs pre-grade |
Revision as of 17:44, 4 January 2023
- Staking of forms - 1 hr for 'supercorners', 2 hours for all rest including string. Superstructure concept works.
- 2 days of forms = 1 day 6 hours 6 people, day 2 from 8 to 1 PM = 66 hours + staking + grading
- Grading - 2 people 6+8 hours = 14 hrs pre-grade
- Smooth for 4 hours - bulk smoothing amd evening
- Finish smooth for 4 hours - getting to a couple inches
- Final smooth 2 hours - finishing off to 2 inches level
Totals
- Grade - 24 hr
- String - 3 hrs
- Foundation forms - 66 hours
- Pour - 4 hrs clusterf*** with 6 people. Initial troublespot was truck getting in right after a sliver of snow made traction difficult so even the 7% small grade did not allow traction. Spread gravel, had to use conveyor to transfer from one truck to another for a stuck truck. Boss came out to help. Mudsill anchors not taped. Forms blew out several inches on one end. Get data for next time.