Line 20: | Line 20: | ||
=Installation - 15 Minutes Per Wall Module= | =Installation - 15 Minutes Per Wall Module= | ||
#Clamp to bottom of next module. Clamp to top of next module. Suck in middle as needed. Use T25 screws | About: | ||
*This process relies on quality controlled modules which are flat to 1-2". | |||
*OSB Master already guarantees edges to be square. | |||
*Leaning in or out - corrected at the top plate-setting level with string line between 2 corners. Braces released in the middle | |||
Process: | |||
#Clamp to bottom of next module. | |||
#Screw working module into base near bottom clamp. | |||
#Clamp to top of next module. | |||
#Suck in middle as needed. Use T25 screws. | |||
#Screw working module at other end - done. | |||
#Add brace for support. 2x4x8s for braces. | |||
#Bump nail it off once quality controlled for module correctness with fiducials and [[Pokayoke]] marking. |
Revision as of 18:27, 4 January 2023
Build Time
- Foundation - 40 hr foundation with grading. 20 hours without grading. 4 hour backhoe, 4 hour gravel, 4 hr rebar, 4 hr staking, 4 hr forms.
- Modules build - 132 hours for 122 modules total. 60 + 18 garage for 1300 sf model. 34 interior modules.
- 10 windows at 2 hours. Rest is one hour average, easy. 112 hours + 20 hours. Including plumbing and electrical!. Total of 132 hours.
- Data from [1] - 3 minutes per member, for 9 members - is a good conservative speed for a carpenter. Build time was 22 minutes with blocking + top/bottom available
- Typical simple modules are 12 members, or 24 minutes
- Windows are ~20 members - 60 minutes for frame.
- Joists - use helper tape premarked for joists. 3D printed blocking later - with recessed screw holes.
- Modules installation - 15 minutes per. See 1 Hour First Floor for data that says 6.3 minutes per team of 2, making it under 15 minutes per person. Thus the 15 minute estimate holds.
Devices
- Helper tape - premarked tape. $5. Green for first floor joists, red for second floor joists, blue for garage joists.
- Winch system
- Power Ladder system
- Bump nailer
- OSB as the Arbiter
- Hole saw set
- Socket set
- Interior modules - prepped with MEP
Installation - 15 Minutes Per Wall Module
About:
- This process relies on quality controlled modules which are flat to 1-2".
- OSB Master already guarantees edges to be square.
- Leaning in or out - corrected at the top plate-setting level with string line between 2 corners. Braces released in the middle
Process:
- Clamp to bottom of next module.
- Screw working module into base near bottom clamp.
- Clamp to top of next module.
- Suck in middle as needed. Use T25 screws.
- Screw working module at other end - done.
- Add brace for support. 2x4x8s for braces.
- Bump nail it off once quality controlled for module correctness with fiducials and Pokayoke marking.