Critical Path Predictions: Difference between revisions
Jump to navigation
Jump to search
Line 3: | Line 3: | ||
=July 8, 2023= | =July 8, 2023= | ||
*[[Critical_Path#May_16.2C_202]] is the last entry, with annual financial planning documented at the [[Seed Eco-Home 4]] business plan under | *[[Critical_Path#May_16.2C_202]] is the last entry, with annual financial planning documented at the [[Seed Eco-Home 4]] business plan under OSE Financial Planning 2023. | ||
*Magic would mean finishing by July 29, and a sale at the same time. | *Magic would mean finishing by July 29, and a sale at the same time. | ||
*Likely scenario involves 30-60 days to finish, due to the overwhelming production engineering being developed: | *Likely scenario involves 30-60 days to finish, due to the overwhelming production engineering being developed: | ||
**Workshop reconstituted for house module production | **Workshop reconstituted for house module production | ||
**Jig for individual modules [https://docs.google.com/presentation/d/1YF44L9WZ75y9LLAr8AwxbeC-K__OKJVt7FZzvzeQQ6Y/edit#slide=id.g22b09dddaa6_1_2] which allows for about 5 minutes per module, thus under 4 hours for the entire house interior walls, and another 4 hours with MEP. | **Jig for individual modules [https://docs.google.com/presentation/d/1YF44L9WZ75y9LLAr8AwxbeC-K__OKJVt7FZzvzeQQ6Y/edit#slide=id.g22b09dddaa6_1_2] which allows for about 5 minutes per module, thus under 4 hours for the entire house interior walls, and another 4 hours with MEP, for a breakthrough 8 hours for interior walls build. | ||
**Key to jig is a measureless edge-protected saw [https://docs.google.com/presentation/d/1YF44L9WZ75y9LLAr8AwxbeC-K__OKJVt7FZzvzeQQ6Y/edit#slide=id.g22b09dddaa6_1_78] | |||
**Overhead hoists takes modules to forks at 8 modules per load, which are then loaded on the trailer [https://docs.google.com/presentation/d/1YF44L9WZ75y9LLAr8AwxbeC-K__OKJVt7FZzvzeQQ6Y/edit#slide=id.g2553fdfac76_0_93]. | |||
**All materials are located right next to the work table and slide right into place, so that from start of build to trailer |
Revision as of 21:46, 8 July 2023
Why Predictions?
- So we can collect data on accuracy of predictions, and wrinkles that get in the way. Should be reviewed monthly or quarterly. Note that milestones and goals are constantly shifting at Critical path with 1 year delays on small milestones, 10 years on larger milestones, and on-time for the largest milestones (2028) which is a nonlinear process. Key is keeping clear on the trillion dollar value proposition of Distributive Economics
July 8, 2023
- Critical_Path#May_16.2C_202 is the last entry, with annual financial planning documented at the Seed Eco-Home 4 business plan under OSE Financial Planning 2023.
- Magic would mean finishing by July 29, and a sale at the same time.
- Likely scenario involves 30-60 days to finish, due to the overwhelming production engineering being developed:
- Workshop reconstituted for house module production
- Jig for individual modules [1] which allows for about 5 minutes per module, thus under 4 hours for the entire house interior walls, and another 4 hours with MEP, for a breakthrough 8 hours for interior walls build.
- Key to jig is a measureless edge-protected saw [2]
- Overhead hoists takes modules to forks at 8 modules per load, which are then loaded on the trailer [3].
- All materials are located right next to the work table and slide right into place, so that from start of build to trailer