Seed Eco-Home 5 Data Collection: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
Line 1: | Line 1: | ||
=Trim Painting= | |||
*Sep 19, 2023 - 1:50 painting setup [https://photos.app.goo.gl/Rrm8jEGNGp1zwuTaA] - 7 sawhorses + 14 sawhorses, all materials laid out - 78 pieces [https://docs.google.com/presentation/d/1kBQLIsBe9Uye9rHgs7BRyxGnlC84mcNt_ON-IqdJ9E4/edit#slide=id.g280d46198e9_1_0] | |||
=Foundation= | |||
*Staking of forms - 1 hr for 'supercorners', 2 hours for all rest including string. Superstructure concept works. | *Staking of forms - 1 hr for 'supercorners', 2 hours for all rest including string. Superstructure concept works. | ||
*2 days of forms = 1 day 6 hours 6 people, day 2 from 8 to 1 PM = 66 hours + staking + grading | *2 days of forms = 1 day 6 hours 6 people, day 2 from 8 to 1 PM = 66 hours + staking + grading |
Revision as of 16:52, 20 September 2023
Trim Painting
- Sep 19, 2023 - 1:50 painting setup [1] - 7 sawhorses + 14 sawhorses, all materials laid out - 78 pieces [2]
Foundation
- Staking of forms - 1 hr for 'supercorners', 2 hours for all rest including string. Superstructure concept works.
- 2 days of forms = 1 day 6 hours 6 people, day 2 from 8 to 1 PM = 66 hours + staking + grading
- Grading - 2 people 6+8 hours = 14 hrs pre-grade
- Smooth for 4 hours - bulk smoothing amd evening
- Finish smooth for 4 hours - getting to a couple inches
- Final smooth 2 hours - finishing off to 2 inches level
Totals
- Grade - 24 hr
- String - 3 hrs
- Foundation forms - 66 hours
- Pour - 4 hrs clusterf*** with 6 people. Initial troublespot was truck getting in right after a sliver of snow made traction difficult so even the 7% small grade did not allow traction. Spread gravel, had to use conveyor to transfer from one truck to another for a stuck truck. Boss came out to help. Mudsill anchors not taped. Forms blew out several inches on one end. Get data for next time.