=Trim Painting=
=Trim Painting=
*Sep 20, 2023 - 6:30. Finished setup - 1 hr setup. 5:30 painting.. Spread boards on horses, added one horse. 5:30 paiting: One side, edges. Flow was to paint accessible side, then paint all of inaccessible side. Then turn boards on edges to paint edges. Best is to take either 2 large ones (12 and 8) or all smaller (6 and 4) and bind with clamp. Tried to paint in place for the edges - doesn't work well as I can not see far edge and have to lean over.M
*Sep 19, 2023 - 1:50 painting setup [https://photos.app.goo.gl/Rrm8jEGNGp1zwuTaA] - 7 sawhorses + 14 sawhorses, all materials laid out - 78 pieces [https://docs.google.com/presentation/d/1kBQLIsBe9Uye9rHgs7BRyxGnlC84mcNt_ON-IqdJ9E4/edit#slide=id.g280d46198e9_1_0]
*Sep 19, 2023 - 1:50 painting setup [https://photos.app.goo.gl/Rrm8jEGNGp1zwuTaA] - 7 sawhorses + 14 sawhorses, all materials laid out - 78 pieces [https://docs.google.com/presentation/d/1kBQLIsBe9Uye9rHgs7BRyxGnlC84mcNt_ON-IqdJ9E4/edit#slide=id.g280d46198e9_1_0]


=Foundation=
=Foundation=

Revision as of 01:09, 21 September 2023

Trim Painting

  • Sep 20, 2023 - 6:30. Finished setup - 1 hr setup. 5:30 painting.. Spread boards on horses, added one horse. 5:30 paiting: One side, edges. Flow was to paint accessible side, then paint all of inaccessible side. Then turn boards on edges to paint edges. Best is to take either 2 large ones (12 and 8) or all smaller (6 and 4) and bind with clamp. Tried to paint in place for the edges - doesn't work well as I can not see far edge and have to lean over.M


  • Sep 19, 2023 - 1:50 painting setup [1] - 7 sawhorses + 14 sawhorses, all materials laid out - 78 pieces [2]

Foundation

  • Staking of forms - 1 hr for 'supercorners', 2 hours for all rest including string. Superstructure concept works.
  • 2 days of forms = 1 day 6 hours 6 people, day 2 from 8 to 1 PM = 66 hours + staking + grading
  • Grading - 2 people 6+8 hours = 14 hrs pre-grade
  • Smooth for 4 hours - bulk smoothing amd evening
  • Finish smooth for 4 hours - getting to a couple inches
  • Final smooth 2 hours - finishing off to 2 inches level

Totals

  • Grade - 24 hr
  • String - 3 hrs
  • Foundation forms - 66 hours
  • Pour - 4 hrs clusterf*** with 6 people. Initial troublespot was truck getting in right after a sliver of snow made traction difficult so even the 7% small grade did not allow traction. Spread gravel, had to use conveyor to transfer from one truck to another for a stuck truck. Boss came out to help. Mudsill anchors not taped. Forms blew out several inches on one end. Get data for next time.