=Trim Painting= | =Trim Painting= | ||
*Sep 21, 2023 - 3 hrs - painting 2nd coat. Mostly bunched 5 to 1 or 2, then did individual board - with face and edges at the same time before moving to the next. | |||
*Sep 20, 2023 - '''6:30 total'''. Finished setup - 1 hr setup: '''22''' minutes move stuff - '''30''' minutes to brush off dirt with brooms. '''5:30''' painting.. Spread boards on horses, added one horse. 5:30 paiting: One side, edges. Flow was to paint accessible side, then paint all of inaccessible side. Then turn boards on edges to paint edges. Best is to take either 2 large ones (12 and 8) or all smaller (6 and 4) and bind with clamp. Tried to paint in place for the edges - doesn't work well as I can not see far edge and have to lean over. More detail: [https://photos.app.goo.gl/Uk6uKXorXAZSZhny5] shows 22 painted 3/4 of the way (walkable part, not on the other side of 'horse barricade'. Took 45 mintues for these 22 - or 2 minutes per. Roller. Rest. Then tried 'broller' = 'brush roller' - use the roller to roll at an angle, so it actually slides and paints like a paintbrush. This is much faster. [https://photos.app.goo.gl/ULw2Tiu8P56NBabi9] shows 25 more done in one hour - these were 12" wide, smooth - not the 8" and 4". Still, about 2 minutes each, but also the 3/4 way per piece because of access (see [https://docs.google.com/presentation/d/1kBQLIsBe9Uye9rHgs7BRyxGnlC84mcNt_ON-IqdJ9E4/edit#slide=id.g24573f9f216_0_162]. '''Summary of acceleration?''': it took 1:45 to paint 47 3/4 of the way. The total number is 78 pieces [https://docs.google.com/presentation/d/1kBQLIsBe9Uye9rHgs7BRyxGnlC84mcNt_ON-IqdJ9E4/edit#slide=id.g280d46198e9_1_0]. Edges are like painting a second time. Roughly, 47*3/4=35. It took 3.75 hr to paint 43 more, but if we 'double it' for the edges - it took 3.75 to paint 121 of them - or 1.8 minutes per, compared to 2.7 minutes per (2 min/0.75). Expectation of the 'broller' route is perhaps 2x as fast as rolling - the broller is a very active process, travel speed is comparable to sprayer though sprayer coverage is wider. It seems that 1.5 minutes is doable, maybe even 1 minute - per board- with the fast route. But edges are also an issue they 'double' the time, possibly triple. It would be best to do edge and face at the same time, it seems. Because it's the time walking around barricade that takes time. We should probably just set up a few horses only, no barricade as workflow is poor with 'barricade.' And eventually, a roller jig for painting boards - just send them through. | *Sep 20, 2023 - '''6:30 total'''. Finished setup - 1 hr setup: '''22''' minutes move stuff - '''30''' minutes to brush off dirt with brooms. '''5:30''' painting.. Spread boards on horses, added one horse. 5:30 paiting: One side, edges. Flow was to paint accessible side, then paint all of inaccessible side. Then turn boards on edges to paint edges. Best is to take either 2 large ones (12 and 8) or all smaller (6 and 4) and bind with clamp. Tried to paint in place for the edges - doesn't work well as I can not see far edge and have to lean over. More detail: [https://photos.app.goo.gl/Uk6uKXorXAZSZhny5] shows 22 painted 3/4 of the way (walkable part, not on the other side of 'horse barricade'. Took 45 mintues for these 22 - or 2 minutes per. Roller. Rest. Then tried 'broller' = 'brush roller' - use the roller to roll at an angle, so it actually slides and paints like a paintbrush. This is much faster. [https://photos.app.goo.gl/ULw2Tiu8P56NBabi9] shows 25 more done in one hour - these were 12" wide, smooth - not the 8" and 4". Still, about 2 minutes each, but also the 3/4 way per piece because of access (see [https://docs.google.com/presentation/d/1kBQLIsBe9Uye9rHgs7BRyxGnlC84mcNt_ON-IqdJ9E4/edit#slide=id.g24573f9f216_0_162]. '''Summary of acceleration?''': it took 1:45 to paint 47 3/4 of the way. The total number is 78 pieces [https://docs.google.com/presentation/d/1kBQLIsBe9Uye9rHgs7BRyxGnlC84mcNt_ON-IqdJ9E4/edit#slide=id.g280d46198e9_1_0]. Edges are like painting a second time. Roughly, 47*3/4=35. It took 3.75 hr to paint 43 more, but if we 'double it' for the edges - it took 3.75 to paint 121 of them - or 1.8 minutes per, compared to 2.7 minutes per (2 min/0.75). Expectation of the 'broller' route is perhaps 2x as fast as rolling - the broller is a very active process, travel speed is comparable to sprayer though sprayer coverage is wider. It seems that 1.5 minutes is doable, maybe even 1 minute - per board- with the fast route. But edges are also an issue they 'double' the time, possibly triple. It would be best to do edge and face at the same time, it seems. Because it's the time walking around barricade that takes time. We should probably just set up a few horses only, no barricade as workflow is poor with 'barricade.' And eventually, a roller jig for painting boards - just send them through. | ||
*Sep 19, 2023 - '''1:50''' painting setup [https://photos.app.goo.gl/Rrm8jEGNGp1zwuTaA] - 7 sawhorses + 14 sawhorses, all materials laid out - 78 pieces [https://docs.google.com/presentation/d/1kBQLIsBe9Uye9rHgs7BRyxGnlC84mcNt_ON-IqdJ9E4/edit#slide=id.g280d46198e9_1_0] | *Sep 19, 2023 - '''1:50''' painting setup [https://photos.app.goo.gl/Rrm8jEGNGp1zwuTaA] - 7 sawhorses + 14 sawhorses, all materials laid out - 78 pieces [https://docs.google.com/presentation/d/1kBQLIsBe9Uye9rHgs7BRyxGnlC84mcNt_ON-IqdJ9E4/edit#slide=id.g280d46198e9_1_0] | ||
Revision as of 16:15, 23 September 2023
Trim Painting
- Sep 21, 2023 - 3 hrs - painting 2nd coat. Mostly bunched 5 to 1 or 2, then did individual board - with face and edges at the same time before moving to the next.
- Sep 20, 2023 - 6:30 total. Finished setup - 1 hr setup: 22 minutes move stuff - 30 minutes to brush off dirt with brooms. 5:30 painting.. Spread boards on horses, added one horse. 5:30 paiting: One side, edges. Flow was to paint accessible side, then paint all of inaccessible side. Then turn boards on edges to paint edges. Best is to take either 2 large ones (12 and 8) or all smaller (6 and 4) and bind with clamp. Tried to paint in place for the edges - doesn't work well as I can not see far edge and have to lean over. More detail: [1] shows 22 painted 3/4 of the way (walkable part, not on the other side of 'horse barricade'. Took 45 mintues for these 22 - or 2 minutes per. Roller. Rest. Then tried 'broller' = 'brush roller' - use the roller to roll at an angle, so it actually slides and paints like a paintbrush. This is much faster. [2] shows 25 more done in one hour - these were 12" wide, smooth - not the 8" and 4". Still, about 2 minutes each, but also the 3/4 way per piece because of access (see [3]. Summary of acceleration?: it took 1:45 to paint 47 3/4 of the way. The total number is 78 pieces [4]. Edges are like painting a second time. Roughly, 47*3/4=35. It took 3.75 hr to paint 43 more, but if we 'double it' for the edges - it took 3.75 to paint 121 of them - or 1.8 minutes per, compared to 2.7 minutes per (2 min/0.75). Expectation of the 'broller' route is perhaps 2x as fast as rolling - the broller is a very active process, travel speed is comparable to sprayer though sprayer coverage is wider. It seems that 1.5 minutes is doable, maybe even 1 minute - per board- with the fast route. But edges are also an issue they 'double' the time, possibly triple. It would be best to do edge and face at the same time, it seems. Because it's the time walking around barricade that takes time. We should probably just set up a few horses only, no barricade as workflow is poor with 'barricade.' And eventually, a roller jig for painting boards - just send them through.
- Sep 19, 2023 - 1:50 painting setup [5] - 7 sawhorses + 14 sawhorses, all materials laid out - 78 pieces [6]
Foundation
- Staking of forms - 1 hr for 'supercorners', 2 hours for all rest including string. Superstructure concept works.
- 2 days of forms = 1 day 6 hours 6 people, day 2 from 8 to 1 PM = 66 hours + staking + grading
- Grading - 2 people 6+8 hours = 14 hrs pre-grade
- Smooth for 4 hours - bulk smoothing amd evening
- Finish smooth for 4 hours - getting to a couple inches
- Final smooth 2 hours - finishing off to 2 inches level
Totals
- Grade - 24 hr
- String - 3 hrs
- Foundation forms - 66 hours
- Pour - 4 hrs clusterf*** with 6 people. Initial troublespot was truck getting in right after a sliver of snow made traction difficult so even the 7% small grade did not allow traction. Spread gravel, had to use conveyor to transfer from one truck to another for a stuck truck. Boss came out to help. Mudsill anchors not taped. Forms blew out several inches on one end. Get data for next time.