Drywall Finishing: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
No edit summary
(Added some more Categories to the page)
 
(One intermediate revision by the same user not shown)
Line 21: Line 21:
**8800 sf*$1.5 = $14k or so in labor.
**8800 sf*$1.5 = $14k or so in labor.
**SEH - about 180 BB sheets?
**SEH - about 180 BB sheets?
=Internal Links=
*[[Drywall Finish Levels]]
[[Category: Drywall]] [[Category: Housing and construction]]

Latest revision as of 14:33, 24 July 2024


HintLightbulb.png Hint: Finishing takes as long as handing, but costs indicate that it is about 2x times the labor of hanging. Hanging is just 1/3 the job. There are different levels of finish. Level 0 is unfinished. Used in some places where looks are not important.

Good

  • How to hang drywall [1]
  • Tape and mud video [2]. Corner strip. 3 coats of mud over every edge or screw. Taping. Corners. Bulk sanding. Edge sanding. Ready to paint. Wow, lots of work.
  • Power roller video - [3]

Time

  • Forbes Home details [4]
  • One wall in a day -[5]. 5 hours for a wall with many penetrations.
  • 7 poeple, 4 days, 1000 sf - 224 hours [6]
  • 144 hrs 1000 sf [7]
  • Amateur takes 2400 hours for 3000 sf house [8]
  • 250-300 sheets with 2 man crew in 8-9 days [9], about half to hang and half to finish.
    • 16 sheets per person per day. 1/2 hr per sheet total.
    • 8800 sf*$1.5 = $14k or so in labor.
    • SEH - about 180 BB sheets?