Seed Eco-Home 4 Calculations: Difference between revisions
Jump to navigation
Jump to search
(30 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
=Various Calculations Spreadsheet= | |||
*Concrete volume, materials lenghts, etc. - [https://docs.google.com/spreadsheets/d/1Cfrrc5A0SGcAtgTibvAQTttDzIQiVehuVGBUIT_1Sq8/edit#gid=0] | |||
=Build Time Spreadsheet= | |||
<html> <iframe src="https://docs.google.com/spreadsheets/d/e/2PACX-1vRSDdtXhjOGd_TjY9HN-OfqlfSLJzp9DHYhy6lJzRk1m6R16-Yjpe8MrpmFOoB_SLyvULcNWmOFw74X/pubhtml?widget=true&headers=false" height=400 width=900></iframe> </html> | |||
[https://docs.google.com/spreadsheets/d/1S0R0OWAR9O3dsC7i-C2MNZxLo9B1AIlQ9f7jwPxLe5o/edit#gid=0 edit] | |||
{{check}}'''Rest of the data needs to be input from [[Seed Eco-Home 4 Data Collection]]''' | |||
=Build Time= | =Build Time= | ||
*'''Foundation - 40 hr''' foundation with grading. 20 hours without grading. 4 hour backhoe, 4 hour gravel, 4 hr rebar, 4 hr staking, 4 hr forms. | *'''Foundation - 40 hr''' foundation with grading. 20 hours without grading. 4 hour backhoe, 4 hour gravel, 4 hr rebar, 4 hr staking, 4 hr forms. | ||
*Modules - ''' | *Modules build - '''118 hours''' for 118 modules total. 60 + 18 garage for 1300 sf model. 40 interior modules. | ||
**10 windows at 2 hours. Rest is one hour average, easy. | **10 windows at 2 hours. Rest is one hour average, easy. 108 hours + 20 hours. '''Including plumbing and electrical!'''. Total of 128 hours. | ||
**Data from [https://photos.google.com/photo/AF1QipPhQYGAhNQJ-tASMVYKJyFUZyyssor55AOhuC6i] - 3 minutes per member, for 9 members - is a good conservative speed for a carpenter. Build time was 22 minutes with blocking + top/bottom available | ***Note that electrical and plumbing may involve up to a dozen components, from cut lists. The assebly station should include spools of wire and tubing, PVC stock, fittings, electrical boxes and devices. A dozen steps at an extra 3 minutes per means about 1/2 hour. For a typical 1/2 hour module - this translates to one hour - within the budget of wall module construction. As far as module stacking, interior modules with [[MEP]] can be stacked vertically for tansport. | ||
**Data from [https://photos.google.com/photo/AF1QipPhQYGAhNQJ-tASMVYKJyFUZyyssor55AOhuC6i] - 3 minutes per member, for 9 members - is a good conservative speed for a carpenter. Build time was 22 minutes with blocking + top/bottom available for these garage modules. | |||
**Typical simple modules are 12 members, or 24 minutes | **Typical simple modules are 12 members, or 24 minutes | ||
**Windows are ~20 members - 60 minutes for frame. | **Windows are ~20 members - 60 minutes for frame. | ||
*Joists - use ''' | *Joists - use '''[[Jig Tape]]''' premarked for joists. 3D printed blocking later - with recessed screw holes. | ||
*Modules installation - 15 minutes per. See [[1 Hour First Floor]] for data that says 6.3 minutes per team of 2, making it under 15 minutes per person. Thus the 15 minute estimate holds. | |||
*Joists and floors x3. First floor, second floor (roof) and garage. 5 minute figure for joist and 4x8 sheet. 22+22+13 sheets = 57 sheets. Joists - 32+32+18=82. 139 total, with 5 min ea, is 695 minutes. 12 hours. | |||
**Assumption of auto material delivery, [[Helper Tape]] | |||
=Devices= | =Devices= | ||
*'''Helper tape''' - premarked tape. [https://www.harborfreight.com/25-ft-x-1-in-quikfind-duralock-tape-measure-60408.html?utm_source=google&utm_medium=cpc&utm_campaign=12169518939&campaignid=12169518939&utm_content=114845734697&adsetid=114845734697&product=60408&store=624&gclid=Cj0KCQiA5NSdBhDfARIsALzs2EBIZB8xT_LQxjFX1lc1ZeRvzAbTsYOBYpJvYtIrA-8et7F7QMbqM98aAqS5EALw_wcB $5]. | *'''Helper tape''' - premarked tape. [https://www.harborfreight.com/25-ft-x-1-in-quikfind-duralock-tape-measure-60408.html?utm_source=google&utm_medium=cpc&utm_campaign=12169518939&campaignid=12169518939&utm_content=114845734697&adsetid=114845734697&product=60408&store=624&gclid=Cj0KCQiA5NSdBhDfARIsALzs2EBIZB8xT_LQxjFX1lc1ZeRvzAbTsYOBYpJvYtIrA-8et7F7QMbqM98aAqS5EALw_wcB $5]. Green for first floor joists, red for second floor joists, blue for garage joists. | ||
*Joist hoist | |||
*[[Drywall Jack]] | |||
*Winch system | |||
*Power Ladder system | |||
*Bump nailer | |||
*OSB as the Arbiter | |||
*Hole saw set | |||
*Socket set | |||
*Interior modules - prepped with [[MEP]] | |||
=Installation - 15 Minutes Per Wall Module= | |||
About: | |||
*This process relies on quality controlled modules which are flat to 1-2". | |||
*OSB Master already guarantees edges to be square. | |||
*Leaning in or out - corrected at the top plate-setting level with string line between 2 corners. Braces released in the middle | |||
Process: | |||
#Clamp to bottom of next module. | |||
#Screw working module into base near bottom clamp. | |||
#Clamp to top of next module. | |||
#Suck in middle as needed. Use T25 screws. | |||
#Screw working module at other end - done. | |||
#Add brace for support. 2x4x8s for braces. | |||
#Bump nail it off once quality controlled for module correctness with fiducials and [[Pokayoke]] marking. | |||
=Concrete Calculator= | |||
#[[Concrete_Calculator]] | |||
= | =Links= | ||
*See [[SH4 Pictures]] |
Latest revision as of 09:35, 19 April 2025
Various Calculations Spreadsheet
- Concrete volume, materials lenghts, etc. - [1]
Build Time Spreadsheet
Rest of the data needs to be input from Seed Eco-Home 4 Data Collection
Build Time
- Foundation - 40 hr foundation with grading. 20 hours without grading. 4 hour backhoe, 4 hour gravel, 4 hr rebar, 4 hr staking, 4 hr forms.
- Modules build - 118 hours for 118 modules total. 60 + 18 garage for 1300 sf model. 40 interior modules.
- 10 windows at 2 hours. Rest is one hour average, easy. 108 hours + 20 hours. Including plumbing and electrical!. Total of 128 hours.
- Note that electrical and plumbing may involve up to a dozen components, from cut lists. The assebly station should include spools of wire and tubing, PVC stock, fittings, electrical boxes and devices. A dozen steps at an extra 3 minutes per means about 1/2 hour. For a typical 1/2 hour module - this translates to one hour - within the budget of wall module construction. As far as module stacking, interior modules with MEP can be stacked vertically for tansport.
- Data from [2] - 3 minutes per member, for 9 members - is a good conservative speed for a carpenter. Build time was 22 minutes with blocking + top/bottom available for these garage modules.
- Typical simple modules are 12 members, or 24 minutes
- Windows are ~20 members - 60 minutes for frame.
- 10 windows at 2 hours. Rest is one hour average, easy. 108 hours + 20 hours. Including plumbing and electrical!. Total of 128 hours.
- Joists - use Jig Tape premarked for joists. 3D printed blocking later - with recessed screw holes.
- Modules installation - 15 minutes per. See 1 Hour First Floor for data that says 6.3 minutes per team of 2, making it under 15 minutes per person. Thus the 15 minute estimate holds.
- Joists and floors x3. First floor, second floor (roof) and garage. 5 minute figure for joist and 4x8 sheet. 22+22+13 sheets = 57 sheets. Joists - 32+32+18=82. 139 total, with 5 min ea, is 695 minutes. 12 hours.
- Assumption of auto material delivery, Helper Tape
Devices
- Helper tape - premarked tape. $5. Green for first floor joists, red for second floor joists, blue for garage joists.
- Joist hoist
- Drywall Jack
- Winch system
- Power Ladder system
- Bump nailer
- OSB as the Arbiter
- Hole saw set
- Socket set
- Interior modules - prepped with MEP
Installation - 15 Minutes Per Wall Module
About:
- This process relies on quality controlled modules which are flat to 1-2".
- OSB Master already guarantees edges to be square.
- Leaning in or out - corrected at the top plate-setting level with string line between 2 corners. Braces released in the middle
Process:
- Clamp to bottom of next module.
- Screw working module into base near bottom clamp.
- Clamp to top of next module.
- Suck in middle as needed. Use T25 screws.
- Screw working module at other end - done.
- Add brace for support. 2x4x8s for braces.
- Bump nail it off once quality controlled for module correctness with fiducials and Pokayoke marking.