== Wednesday, September 07 (3:39) == | |||
*Need to ship out a tractor. Mounting for the new powercube. | |||
*Engine tests(2 Hours) | |||
*Shakedown New Welder | |||
*Powercube Assembly overview | |||
*Cut Tabs for tanks | |||
*Brianna working on CEB | |||
== Tuesday, September 06 (4:45) == | |||
*Money ain't in! Emergency mode! | |||
*power cubes explosions! | |||
*Galvanized Fittings for power cubes. | |||
**BAD IDEA - Needs constant rewelding. Non-galvanized works on the first try. | |||
*Brianna staying till saturday. | |||
*[[Power Cube Tank Welding Procedure]] | |||
*OOOh Harbor Freight cheap mini 190 amp welders! Supply run! | |||
<html> | |||
<iframe width="200" height="142" src="https://www.youtube.com/embed//XzAIuei6qpM" frameborder="0" allowfullscreen></iframe> | |||
</html> | |||
== Monday, September 05 (3:30) == | |||
*Brianna taking over the [[Backhoe]] project | |||
*[[OSE]] project [[Deliverables]] | |||
*Goal to finalize [[CEB Press]] CAD ready for publishing tomorrow | |||
*Shanda working on MultiMachine, cadding up Solidworks (finally got working). | |||
*Chris clearing off platter for [[3D Printer]] next week. (Carana, Power Cube, CEB, wiki, documentation) | |||
*Cut Lists (hopper pieces) | |||
*Marcin - Cleaning up Power Cube Tank bungs (delays). | |||
== Sunday == | |||
*Day off. | |||
== Saturday, September 03 (12:59) == | == Saturday, September 03 (12:59) == | ||
*Similar to yesterday | *Similar to yesterday | ||
Line 5: | Line 41: | ||
**CEB Roller Design | **CEB Roller Design | ||
**''Yo Mama'' Construction Methods | **''Yo Mama'' Construction Methods | ||
*Shopping List | |||
** | |||
== Friday, September 02 (4:30) == | == Friday, September 02 (4:30) == |
Latest revision as of 00:24, 3 July 2012
Wednesday, September 07 (3:39)
- Need to ship out a tractor. Mounting for the new powercube.
- Engine tests(2 Hours)
- Shakedown New Welder
- Powercube Assembly overview
- Cut Tabs for tanks
- Brianna working on CEB
Tuesday, September 06 (4:45)
- Money ain't in! Emergency mode!
- power cubes explosions!
- Galvanized Fittings for power cubes.
- BAD IDEA - Needs constant rewelding. Non-galvanized works on the first try.
- Brianna staying till saturday.
- Power Cube Tank Welding Procedure
- OOOh Harbor Freight cheap mini 190 amp welders! Supply run!
Monday, September 05 (3:30)
- Brianna taking over the Backhoe project
- OSE project Deliverables
- Goal to finalize CEB Press CAD ready for publishing tomorrow
- Shanda working on MultiMachine, cadding up Solidworks (finally got working).
- Chris clearing off platter for 3D Printer next week. (Carana, Power Cube, CEB, wiki, documentation)
- Cut Lists (hopper pieces)
- Marcin - Cleaning up Power Cube Tank bungs (delays).
Sunday
- Day off.
Saturday, September 03 (12:59)
- Similar to yesterday
- Hab Lab Update
- Estimates
- CEB Roller Design
- Yo Mama Construction Methods
- Shopping List
Friday, September 02 (4:30)
- Power Cubes almost done!
- Finish leak testing on tanks
- Checkoff on cuts
- Frames all welded
- Wiring Instructions
- Battery Cables
- Throttle Mounts
- Filter Assembly Instructions
- Assembly and Weld!
- Build right behind tractors for easier mounting.
- Goal to finish power cubes by end of today.
- Whiteboards
- Bakers supply run.
Wednesday, August 31 (6:10 PM)
- Welcome Bruce Baker!
- Power Cube Inventory
- Shopping list
Monday, August 29 (3:20 PM)
- Funding delays
- Strategies with priorities (Prototyping, Documentation, Enterprise Training)
- Brianna's todo list (see Brianna Log
- Retorching undersized feet holder
- Hopper Plates
- Welder shakedown.
- Install Drawers
- Chris going on a supply run (Nuts, Fans, Muffler Pipe)
Wednesday, August 24 (began at 7:15 PM)
- Discussion about progress on personal wiki logs and also progress made by Chris and Tom. Problems with using Media Wiki.
- Shonda added picture to wiki log - and gained praise.
- Discussed progress made on Power Cube documentation and problems encountered with wiki and graphics.
- New and improved labor standards mandate 1 to 3 hours of "real work" in the OSE community.
- Discussion about cleaning up the grounds, recycling the tin cans, glass, burning trash, etc.
- Certified welders will arrive soon to help the effort.
Tuesday, August 23 (began at 5:20 PM)
- Discussed importance of wiki logs for each participant
- Spent time reviewing others' wikis, updating and giving suggestions for enhancements
- Discussed trip to Sweigert Shop and progress made there
- Discussed "to do" items for everyone:
- Tom to get with Chris for graphics for the documentation
- Chris to research milling machines, including new makes
- Brianna and Marcin to move equipment to new workshop building
Monday, August 22 (began at 4:10 PM)
- Discussed everyone's access to the wiki Logs - some were still lacking and followed up on getting everyone's log updated.
- Discussed documentation efforts for Power Cube and CEB press. Tom said the biggest delays were in graphics and distractions.
- Discussed to do tasks:
- Tom - test electronics
- Shonda - investigate milling machines for purchase
- Briana - finalize CEB press
- Everyone - Help with new structure, adding extenders to roof
Sunday, August 21 (began about 5:00 PM)
- The first part of meeting addressed wiki and that everyone needs to be maintaining log entries for their participation.
- The discussion then went into the tasks to be performed.
- Then discussed immediate to do list - the first task was to work on the roof for the new shop space.