==December 2012==
==December 2012==
December 31, 2012
December 31, 2012
Sent [[Open_source_bioplastic_2012_update |Open source bioplastic 2012 update. Updated polylactic acid system engineering diagrams. Added decent melt solid review to literature review. Working on lit. review formatting for inline citations.
 
Sent [[open_source_bioplastic_2012_update |Open source bioplastic 2012 update]]. Updated polylactic acid system engineering diagrams. Added decent melt solid review to literature review. Working on lit. review formatting for inline citations.


December 28, 2012
December 28, 2012
Finished collaborator update email to be sent in the next few days. Organizing literature review and filling in gaps. Organizing project for material implementation.
Finished collaborator update email to be sent in the next few days. Organizing literature review and filling in gaps. Organizing project for material implementation.

Revision as of 18:33, 31 December 2012

Worklog

EDIT

To Do

December

  • Year end collaborator update

January

  • Finalize literature review/ background information
    • Transwiki to appropedia
  • Finalize necessary equipment and materials
    • Communicate with Pearce group to determine available equipment
    • Cost of materials to be purchased - create estimated budget

February-April

  • Finalize process procedures
    • Optimization steps
    • Interesting open questions

May-July

  • Material implementation
    • Build fermentor
    • Production sprint at MTU

Daily Log

December 2012

December 31, 2012

Sent Open source bioplastic 2012 update. Updated polylactic acid system engineering diagrams. Added decent melt solid review to literature review. Working on lit. review formatting for inline citations.

December 28, 2012

Finished collaborator update email to be sent in the next few days. Organizing literature review and filling in gaps. Organizing project for material implementation.