==July 15== | |||
*Continued work on the [https://github.com/LovingProfessional/Open-CEB-Press code] of the CEB controller | |||
*Welded lots and lots of clamps together | |||
==July 10== | |||
*Positioned primary arms | |||
*Retrieved and assembled pipe clamps from menards | |||
==July 11== | |||
*Performed diagnostic work on the power cube | |||
==July 13== | |||
*Bored holes in various CEB parts | |||
*Began coding test procedures for the CEB press | |||
==July 14== | |||
*Bored holes in CEB parts | |||
*Created test procedures and began working on automated procedure | |||
==June 25== | |||
*Performed further test cuts | |||
*Added a prototype for adjustment of pierce time | |||
*Added an interface for z axis control through Lasersaur App | |||
==June 24== | |||
*Continued Overall assembly module | |||
*Completed grouping of latest CEB press fcstd | |||
*Temporarily fixed a problem with the Torch table path ordering. Paths can be ordered modified with svg editor inkscape prior to export. Tools such as gcodetools | |||
*Performed several test cuts | |||
==June 23== | |||
*Added a tut on the [[GIMP]] page | |||
*Added a tutorial to download the latest version of [[FreeCAD]] | |||
*Weeded lots | |||
*Wrote instructional for gas operation of Torch Table | |||
*Began partitioning of new CEB model | |||
*Cleared out the solar house and organized contents | |||
*Discussed future innovations to collaborative architecture | |||
==June 20== | |||
*Built silk screen frame and scoop cup | |||
*Sealed holes in solar house | |||
==June 19== | |||
*Weeded | |||
*Moved supplies from solar house | |||
*Applied a layer of paint to the bottom | |||
==June 18== | |||
*Applied two layers of stain to the solar house siding | |||
*Went dumpster diving in St. Joseph for screen printing supplies | |||
==June 17== | |||
*Finished side paneling on the solar house | |||
*Picked up supplies for screen printed shirts | |||
==June 16== | |||
*Helped to load van | |||
*Took stock of CEB press pieces | |||
*Fastened side paneling to the sun house | |||
*Picked up food supplies, wood finish, more paneling etc | |||
==June 14== | |||
*Puked and slept | |||
==June 13== | |||
*Puked and slept | |||
==June 12== | |||
*Made changes to grate instructional | |||
*Did research on visual VC and alternative CAD programs and formats | |||
*Built automatic gcode modification into LasersaurApp and explored the code. Thoroughly. | |||
==June 11== | ==June 11== | ||
*Created an instructional for the [https://docs.google.com/presentation/d/1fcz4_t0VDfm1RMY2C63SHj6NWFTicd-gledlzG05tok/edit#slide=id.g34f913ef9_15 Grate deflector module] | *Created an instructional for the [https://docs.google.com/presentation/d/1fcz4_t0VDfm1RMY2C63SHj6NWFTicd-gledlzG05tok/edit#slide=id.g34f913ef9_15 Grate deflector module] | ||
Line 35: | Line 108: | ||
==June 4== | ==June 4== | ||
*Finished | *Finished instructional for the [https://docs.google.com/presentation/d/1V5zQif5GMfydl2p3LVO-s_WBr8nLeWkq6JpC0VZq2HM CEB Grate] | ||
*Installed new internet connection from the mud huts (Nope, broken again, will fix tomorrow) | *Installed new internet connection from the mud huts (Nope, broken again, will fix tomorrow) | ||
*Implanted gcode into the torch table for testing purposes. | *Implanted gcode into the torch table for testing purposes. | ||
Line 65: | Line 138: | ||
*Update calender | *Update calender | ||
*NOLS Prereqs | *NOLS Prereqs | ||
[[Category:Logs]] |
Latest revision as of 01:24, 24 January 2016
July 15
- Continued work on the code of the CEB controller
- Welded lots and lots of clamps together
July 10
- Positioned primary arms
- Retrieved and assembled pipe clamps from menards
July 11
- Performed diagnostic work on the power cube
July 13
- Bored holes in various CEB parts
- Began coding test procedures for the CEB press
July 14
- Bored holes in CEB parts
- Created test procedures and began working on automated procedure
June 25
- Performed further test cuts
- Added a prototype for adjustment of pierce time
- Added an interface for z axis control through Lasersaur App
June 24
- Continued Overall assembly module
- Completed grouping of latest CEB press fcstd
- Temporarily fixed a problem with the Torch table path ordering. Paths can be ordered modified with svg editor inkscape prior to export. Tools such as gcodetools
- Performed several test cuts
June 23
- Added a tut on the GIMP page
- Added a tutorial to download the latest version of FreeCAD
- Weeded lots
- Wrote instructional for gas operation of Torch Table
- Began partitioning of new CEB model
- Cleared out the solar house and organized contents
- Discussed future innovations to collaborative architecture
June 20
- Built silk screen frame and scoop cup
- Sealed holes in solar house
June 19
- Weeded
- Moved supplies from solar house
- Applied a layer of paint to the bottom
June 18
- Applied two layers of stain to the solar house siding
- Went dumpster diving in St. Joseph for screen printing supplies
June 17
- Finished side paneling on the solar house
- Picked up supplies for screen printed shirts
June 16
- Helped to load van
- Took stock of CEB press pieces
- Fastened side paneling to the sun house
- Picked up food supplies, wood finish, more paneling etc
June 14
- Puked and slept
June 13
- Puked and slept
June 12
- Made changes to grate instructional
- Did research on visual VC and alternative CAD programs and formats
- Built automatic gcode modification into LasersaurApp and explored the code. Thoroughly.
June 11
- Created an instructional for the Grate deflector module
- Fixed the HyrdaFabber 3D printer-- flashed the firmware, cleaned the hotend, re-wound the spool and re-leveled the bed.
June 10
- Worked to level the Ultimaker 3d printer
- Got pronterface working on Linux
- Unpacked pool parts and began to take inventory
- Augmented the pool assembly instructional
June 9
- Moved pool parts
- Assisted in torch table configuration
June 8
- Penetration test of CNC torch table
- Continued through KiCad Tutorials
- Continued devpage dozuki scraper
June 7
- Worked through KiCad tutorials
- Documented and assisted power cube dis-assembly
- Built automated web scraper to coalesce devpages
June 6
- Configured wireless access point in FabLab
- Took Video documentation on CNC Torch Table and assisted with testing
- Made a tutorial for using xchat on the collaboration architecture presentation
June 5
- Configured two routers in hablab [1]
- Began work on consolidating work logs
- Began refinement of Torch cutter goals and documentation of recent development here
June 4
- Finished instructional for the CEB Grate
- Installed new internet connection from the mud huts (Nope, broken again, will fix tomorrow)
- Implanted gcode into the torch table for testing purposes.
June 3
- Organized power tool and began to label shelves and drawers
- Began construction and time lapse of Liberator
- Found potential solutions to implanting a modified gcode file manually to the torchtable
- Researched burying a cat5 cable (notes)
June 2
- Augmented the Collaboration Architecture slideshow to include instructions about installing SketchUp on Ubuntu 12.04
- Recorded and participated in Liberator deconstruction time lapse
- Assisted in Ubuntu installations
- Recorded extension cord salvation
- Planted tomatoes and soy
June 1
- Constructed a proposal for youtube raw media upload standards
Ongoing todo list
- Polish youtube raw uploads specifications
- Continue to upload to Trovebox
- Push IRC
- Upload CNC Torch table documentation
- Learn KiCode
- Find way of going from FreeCad to Sketchup Vice Versa
- Update calender
- NOLS Prereqs