Line 3: | Line 3: | ||
#Gravel cost - 30k dg = $15k | #Gravel cost - 30k dg = $15k | ||
#Building Cost - platform on edges with 8x16 units. See [[6_Bath_6_Shower#BOM]] for base platform | #Building Cost - platform on edges with 8x16 units. See [[6_Bath_6_Shower#BOM]] for base platform | ||
#Working out cost of 2 month package. Working out detail of 2 month package layout. | |||
#Can we do layout of existing Seed Eco-Home? |
Latest revision as of 22:53, 20 May 2025
Tue May 20, 2025
- Dozer rental for 20k sf building. Start BOM + design.
- Gravel cost - 30k dg = $15k
- Building Cost - platform on edges with 8x16 units. See 6_Bath_6_Shower#BOM for base platform
- Working out cost of 2 month package. Working out detail of 2 month package layout.
- Can we do layout of existing Seed Eco-Home?